NATIONAL BUILDING CONST. CORPN. vs S RAGHUNATHAN — C.A. No. 4483/1998
Case under Section XIV-A. Status: DISPOSED.
CNR: SCIN010047451997
Filing Date
13-Mar-1997
Registration No
C.A. No. 4483/1998
Diary Number
4745/1997
Order Date
28-Aug-1998
Document Type
Judgment - of Main Case
Disposal Type
Dismissed
Data as of 02-Jun-2026
Acts & Sections
Petitioner(s)
NATIONAL BUILDING CONST. CORPN.
Adv. RAVINDRA KUMAR (Dead / Retired / Elevated)
Respondent(s)
S RAGHUNATHAN
Adv. C. V. SUBBA RAO V. J. FRANCIS (Dead / Retired / Elevated)
Orders
Case Summary: NBCC v. S. Raghunathan (1998) The Supreme Court reversed the Delhi High Court's order directing NBCC to pay Foreign Allowance at 125% of revised basic pay to employees deputized to Iraq. The Court held that Foreign Allowance was not part of the original deputation agreement and constituted a discretionary compensatory allowance under Fundamental Rule 51(2), not a salary component. NBCC's policy decision to freeze Foreign Allowance at pre-revised pay rates was upheld as a valid exercise of discretion based on Iraq's financial conditions, rejecting the respondents' "legitimate expectation" doctrine claim as insufficiently pleaded and speculative. This case analysis is maintained by casestatus.in based on publicly available court records.