N T P C LTD. vs CEN.ELECT REGUL.COMMN.. — C.A. No. 3550/2007
Case under Section I-B. Status: DISPOSED.
CNR: SCIN010174452007
Filing Date
19-Jun-2007
Registration No
C.A. No. 3550/2007
Diary Number
17445/2007
Order Date
02-Dec-2010
Document Type
ROP - of Main Case
Disposal Type
Disposed Off
Data as of 30-Jun-2026
Acts & Sections
Petitioner(s)
N T P C LTD.
Adv. K. V. MOHAN
Respondent(s)
CEN.ELECT REGUL.COMMN..
Adv. M. T. GEORGE
Orders
Case Summary: NTPC LTD v. Central Electricity Regulatory Commission Hearing Date: 2 December 2010 Outcome: The Supreme Court disposed of NTPC's appeal by remitting the matter back to the Appellate Tribunal for Electricity for reconsideration. The Tribunal had previously rejected NTPC's claim for Rs. 370.30 crores in capital expenditure (as of April 1, 2004) for establishing corporate and regional offices, deeming it too late to raise. The Court found that two critical issues were not addressed by the Tribunal: (1) whether NTPC could claim future benefits from the capital expenditure despite the retrospective period bar, and (2) whether applicable regulations permit such claims at all. The Court directed the Tribunal to specifically record findings on these concurrent, inter-connected issues and decide expeditiously. This case analysis is maintained by casestatus.in based on publicly available court records.
Browse Related Cases
Explore other courts