STATE OF MADHYA PRADESH vs M/S S.P. SINGLA CONSTRUCTION PVT. LTD. THR. DIRECTOR — C.A. No. 8731/2017

Case under Section III. Status: Disposed.

Disposed

CNR: SCIN010131462013

Filing Date

23-Apr-2013

Registration No

C.A. No. 8731/2017

Diary Number

13146/2013

Order Date

17-Feb-2022

Document Type

ROP - of Main Case

Disposal Type

Disposed Off

Last updated 06-Jul-2026

Acts & Sections

Section III

Petitioner(s)

  1. 1.STATE OF MADHYA PRADESH

    Adv. SUNNY CHOUDHARY[P-1] [Gr]

Respondent(s)

  1. 1.M/S S.P. SINGLA CONSTRUCTION PVT. LTD. THR. DIRECTOR

    Adv. LIZ MATHEW (Dead / Retired / Elevated) [R-1]

Case History

  1. Case disposedDisposed

  2. 17-Feb-2022

    ROP - of Main CaseView PDF

  3. 17-Feb-2022

    Fixed Date by Court

    Hon'ble The Chief Justice, Hon'ble Mr. Justice A.S. Bopanna and Hon'ble Ms. Justice Hima Kohli

  4. 16-Feb-2022

    ROP - of Main CaseView PDF

  5. 16-Feb-2022

    After Week/Month/Vacation

    Hon'ble The Chief Justice, Hon'ble Mr. Justice A.S. Bopanna and Hon'ble Ms. Justice Hima Kohli

  6. 15-Dec-2021

    ROP - of Main CaseView PDF

  7. 15-Dec-2021

    Next Week / Week Commencing / C.O.Week

    Hon'ble The Chief Justice, Hon'ble Mr. Justice A.S. Bopanna and Hon'ble Ms. Justice Hima Kohli

  8. 02-Dec-2019

    ROP - of Main CaseView PDF

  9. 23-Aug-2019

    ROP - of Main CaseView PDF

  10. 23-Aug-2019

    Fixed Date by Court

    Hon'ble Mr. Justice Abhay Manohar Sapre and Hon'ble Mr. Justice R. Subhash Reddy

  11. 06-Jul-2017

    ROP - of Main CaseView PDF

  12. 06-Jul-2017

    Fixed Date by Court

    Hon'ble Mr. Justice Abhay Manohar Sapre and Hon'ble Mrs. Justice R. Banumathi

  13. 04-Jul-2017

    ROP - of Main CaseView PDF

  14. 04-Jul-2017

    First hearing

    Initial hearing scheduled

  15. 23-Aug-2016

    Office Report - of Main CaseView PDF

  16. 04-Jul-2016

    ROP - of Main CaseView PDF

  17. 04-Jul-2016

    Office Report - of Main CaseView PDF

  18. 04-Jul-2016

    ROP - of Main CaseView PDF

  19. 30-Jun-2016
  20. 30-Jun-2016
  21. 10-Oct-2014

    ROP - of Main CaseView PDF

  22. 10-Oct-2014

    Office Report - of Main CaseView PDF

  23. 10-Oct-2014

    Office Report - of Main CaseView PDF

  24. 10-Oct-2014

    ROP - of Main CaseView PDF

  25. 28-Aug-2014

    ROP - of Main CaseView PDF

  26. 28-Aug-2014

    ROP - of Main CaseView PDF

  27. 30-Jul-2014

    ROP - of Main CaseView PDF

  28. 23-Apr-2014

    ROP - of Main CaseView PDF

  29. 27-Jan-2014

    ROP - of Main CaseView PDF

  30. 13-Dec-2013

    Office ReportView PDF

  31. 13-Dec-2013
  32. 04-Oct-2013

    ROP - of Main CaseView PDF

  33. 30-Sep-2013
  34. 23-Apr-2013

    Case filed

    Registration No. C.A. No. 8731/2017

casestatus.in Summary

Case Summary: C.A. No. 008731/2017 Outcome: The Supreme Court disposed of both appeals (CA 8731 and 8732 of 2017) by directing the State of Madhya Pradesh to pay Rs. 2 crores and Rs. 4 crores respectively to M/S S.P. Singla Construction Pvt. Ltd. as full and final settlement of arbitral awards dated 28.02.2009 and 07.03.2009, instead of awarding full principal plus accrued 8% interest (Rs. 2.63 crores and Rs. 4.6 crores respectively). Next Steps: The State must remit the settlement amounts within six weeks from February 17, 2022. The pending interlocutory application was also disposed of accordingly. This case analysis is maintained by casestatus.in based on publicly available court records.