Sukumaran vs KSEB rep by Secretary — 200244/2019
Case under Code of Civil Procedure Section O7,R1,S26. Status: For commission report. Next hearing: 27th July 2026.
OS - ORIGINAL SUIT
CNR: KLAL110005602019
Filing Number
200631/2019
Filing Date
25-May-2019
Registration No
200244/2019
Registration Date
25-May-2019
Court
Munsiff Court, Cherthala
Judge
2-Additional Munsiff, Cherthala
Last updated 15-Jun-2026
Acts & Sections
Petitioner(s)
-
1.Sukumaran
Adv. SUBHANGAN. V. N
-
2.Reshma
Respondent(s)
-
1.KSEB rep by Secretary
-
2.Assistant Executive Engineer, Kerala State Electricity Board
-
3.Assistant Engineer
Case History
-
27-Jul-2026
Next hearingPending
-
09-Jun-2026
For commission report
Additional Munsiff, Cherthala
-
16-Mar-2026
For commission report
Additional Munsiff, Cherthala
-
18-Feb-2026
For commission report
Additional Munsiff, Cherthala
-
28-Jan-2026
For commission report
Additional Munsiff, Cherthala
-
06-Jan-2026
For commission report
Additional Munsiff, Cherthala
-
01-Dec-2025
For commission report
Additional Munsiff, Cherthala
-
03-Nov-2025
Adjourned
Additional Munsiff, Cherthala
-
09-Oct-2025
Objection
Additional Munsiff, Cherthala
-
10-Sep-2025
Final OrderView PDF
-
10-Sep-2025
Final OrderView PDF
Case Summary: Sukumaran and Reshma filed an interim application seeking police assistance to stop construction works by Kerala State Electricity Board (KSEB) on their properties, alleging violation of a status quo order. The court dismissed the application as infructuous after a commission report revealed the construction works were already completed, rendering the relief sought moot. This case analysis is maintained by casestatus.in based on publicly available court records.
-
10-Sep-2025
For Objection and hearing
Additional Munsiff, Cherthala
-
16-Aug-2025
Order In IA
Additional Munsiff, Cherthala
-
12-Aug-2025
For Hearing
Additional Munsiff, Cherthala
-
07-Aug-2025
For Hearing
Additional Munsiff, Cherthala
-
06-Aug-2025
For Hearing
Additional Munsiff, Cherthala
-
18-Jul-2025
For Objection and hearing
Additional Munsiff, Cherthala
-
29-May-2025
Objection
Additional Munsiff, Cherthala
-
27-Mar-2025
Objection
Additional Munsiff, Cherthala
-
26-Mar-2025
Order In IA
Additional Munsiff, Cherthala
-
01-Mar-2025
For commission report
Additional Munsiff, Cherthala
-
05-Feb-2025
OrderView PDF
-
05-Feb-2025
OrderView PDF
-
05-Feb-2025
For commission Application
Additional Munsiff, Cherthala
-
29-Jan-2025
Order In IA
Additional Munsiff, Cherthala
-
17-Jan-2025
For Hearing
Additional Munsiff, Cherthala
-
05-Dec-2024
For Objection and hearing
Additional Munsiff, Cherthala
-
12-Nov-2024
For Objection and hearing
Additional Munsiff, Cherthala
-
29-Aug-2024
For Objection and hearing
Additional Munsiff, Cherthala
-
19-Jul-2024
For Objection and hearing
Additional Munsiff, Cherthala
-
11-Jun-2024
Pre trial steps
Additional Munsiff, Cherthala
-
20-Feb-2024
Bcf and steps
Additional Munsiff, Cherthala
-
18-Dec-2023
Issues
Additional Munsiff, Cherthala
-
04-Oct-2023
Appearance Of Parties
Additional Munsiff, Cherthala
-
20-Sep-2023
Appearance Of Parties
Additional Munsiff, Cherthala
-
29-Jul-2023
Written Statement
Additional Munsiff, Cherthala
-
29-May-2023
Written Statement
Additional Munsiff, Cherthala
-
09-Jan-2023
Written Statement
Additional Munsiff, Cherthala
-
12-Oct-2022
Return of summons
Additional Munsiff, Cherthala
-
14-Jul-2022
Return of summons
Additional Munsiff, Cherthala
-
14-Jun-2022
Return of summons
Additional Munsiff, Cherthala
-
01-Jun-2022
For Objection and hearing
Additional Munsiff, Cherthala
-
11-Mar-2022
For Objection and hearing
Additional Munsiff, Cherthala
-
25-Feb-2022
For Objection and hearing
Additional Munsiff, Cherthala
-
18-Dec-2021
For Objection and hearing
Additional Munsiff, Cherthala
-
26-Oct-2021
For Objection and hearing
Additional Munsiff, Cherthala
-
11-Oct-2021
For Hearing
Additional Munsiff, Cherthala
-
02-Jul-2021
For Objection and hearing
Additional Munsiff, Cherthala
-
29-Jan-2021
Return of summons
Additional Munsiff, Cherthala
-
27-Oct-2020
Return of summons
Additional Munsiff, Cherthala
-
10-Jul-2020
Return of summons
Additional Munsiff, Cherthala
-
19-Mar-2020
Return of summons
Additional Munsiff, Cherthala
-
18-Jan-2020
Return of summons
Additional Munsiff, Cherthala
-
19-Sep-2019
Written Statement
Additional Munsiff, Cherthala
-
09-Jul-2019
Written Statement
Additional Munsiff, Cherthala
-
24-Jun-2019
Call on
Additional Munsiff, Cherthala
-
21-Jun-2019
For Objection and hearing
Additional Munsiff, Cherthala
-
07-Jun-2019
For Objection and hearing
Additional Munsiff, Cherthala
-
25-May-2019
First hearing
Initial hearing scheduled
-
25-May-2019
Case filed
Registration No. 200244/2019
Case Summary: Sukumaran and Reshma filed an interim application seeking police assistance to stop construction works by Kerala State Electricity Board (KSEB) on their properties, alleging violation of a status quo order. The court dismissed the application as infructuous after a commission report revealed the construction works were already completed, rendering the relief sought moot. This case analysis is maintained by casestatus.in based on publicly available court records.
Explore other courts