Jyoti W/o Basavaraj Choori Age 65Yrs Occ Agri R/o Ballundagi Tq Jewargi Dist Kalaburagi. vs ASSISTANT EXRCUTIVE ENGINEER KBJNL(J.B.C.) Division No.3 R/o Chigharalli Tq Jewargi Dist Klb — 172/2024
Case under Code of Civil Procedure Section 7,1,26. Status: Evidence-CIVIL. Next hearing: 12th June 2026.
O.S. - Original Suit
CNR: KAKB620032152024
e-Filing Number
13-12-2024
Filing Number
172/2024
Filing Date
13-Dec-2024
Registration No
172/2024
Registration Date
18-Dec-2024
Court
PRL. CIVIL JUDGE AND JMFC, JEVARGI
Judge
328-CIVIL Judge JMFC,Jewargi
Last updated 13-Mar-2026
Acts & Sections
Petitioner(s)
-
1.Jyoti W/o Basavaraj Choori Age 65Yrs Occ Agri R/o Ballundagi Tq Jewargi Dist Kalaburagi.
Adv. SHEKAPPA M MALAGATTI
Respondent(s)
-
1.ASSISTANT EXRCUTIVE ENGINEER KBJNL(J.B.C.) Division No.3 R/o Chigharalli Tq Jewargi Dist Klb
-
2.Mutthu M Mundewadgi Age Major R/o Annapurneshwari Nagar Bandal Road Sindagi
Case History
-
12-Jun-2026
Next hearingPending
-
06-Mar-2026
Evidence-CIVIL
CIVIL Judge JMFC,Jewargi
-
09-Jan-2026
Evidence-CIVIL
CIVIL Judge JMFC,Jewargi
-
13-Nov-2025
Evidence-CIVIL
CIVIL Judge JMFC,Jewargi
-
22-Aug-2025
Evidence-CIVIL
CIVIL Judge JMFC,Jewargi
-
05-Jul-2025
Evidence-CIVIL
CIVIL Judge JMFC,Jewargi
-
23-Apr-2025
Issues.
CIVIL Judge JMFC,Jewargi
-
29-Mar-2025
Issues.
CIVIL Judge JMFC,Jewargi
-
17-Feb-2025
OrdersView PDF
Case Summary Case: O.S.No.172/2024 Outcome: Interim Application No. II (seeking to prevent construction of a south-north oriented canal on plaintiff's property Survey No. 64/1) dismissed with costs of Rs. 1,000. The court found that the canal construction is a public utility project under the Krishna Upper Dam scheme for which the government acquired land in 2003, and therefore no injunction can be granted to obstruct such infrastructure work under the Specific Relief Act, 1963. This case analysis is maintained by casestatus.in based on publicly available court records.
-
17-Feb-2025
Issues.
CIVIL Judge JMFC,Jewargi
-
13-Feb-2025
Hearing
CIVIL Judge JMFC,Jewargi
-
12-Feb-2025
Hearing
CIVIL Judge JMFC,Jewargi
-
23-Jan-2025
Hearing
CIVIL Judge JMFC,Jewargi
-
13-Jan-2025
Summons
CIVIL Judge JMFC,Jewargi
-
04-Jan-2025
Summons
CIVIL Judge JMFC,Jewargi
-
19-Dec-2024
Summons
CIVIL Judge JMFC,Jewargi
-
18-Dec-2024
First hearing
Initial hearing scheduled
-
13-Dec-2024
Case filed
Registration No. 172/2024
Case Summary Case: O.S.No.172/2024 Outcome: Interim Application No. II (seeking to prevent construction of a south-north oriented canal on plaintiff's property Survey No. 64/1) dismissed with costs of Rs. 1,000. The court found that the canal construction is a public utility project under the Krishna Upper Dam scheme for which the government acquired land in 2003, and therefore no injunction can be granted to obstruct such infrastructure work under the Specific Relief Act, 1963. This case analysis is maintained by casestatus.in based on publicly available court records.
Explore other courts