PGVCL vs SOLANKI CHANABHAI MADHABHAI — 88/2025
Case under Code of Civil Procedure Section 1. Disposed: Uncontested--JUDGEMENT on 20th April 2026.
RCS - REGULAR CIVIL SUIT
CNR: GJDW060015002025
Filing Number
88/2025
Filing Date
01-12-2025
Registration No
88/2025
Registration Date
01-12-2025
Court
TALUKA COURT, BHANVAD
Judge
1-PRINCIPAL CIVIL JUDGE & J.M.F.C
Decision Date
20th April 2026
Nature of Disposal
Uncontested--JUDGEMENT
Acts & Sections
Petitioner(s)
PGVCL
Adv. M T NANAVATI
Respondent(s)
SOLANKI CHANABHAI MADHABHAI
Hearing History
Judge: 1-PRINCIPAL CIVIL JUDGE & J.M.F.C
Disposed
FINAL ARGUMENTS
FINAL ARGUMENTS
PLAINTIFF EVIDENCE
PLAINTIFF EVIDENCE
| Date | Purpose |
|---|---|
| 20-04-2026 | Disposed |
| 14-03-2026 | FINAL ARGUMENTS |
| 16-02-2026 | FINAL ARGUMENTS |
| 19-01-2026 | PLAINTIFF EVIDENCE |
| 29-12-2025 | PLAINTIFF EVIDENCE |
Final Orders / Judgements
Case Summary: 88/2025 (PGVCL v. Solanki Chanabhai Madhabhai) The court partially allowed PGVCL's electricity recovery suit against the respondent. The court found the respondent liable for unpaid electricity dues of ₹8,433.04 with 6% annual interest from the billing date until payment, rejecting PGVCL's claim for 16% interest due to lack of contractual agreement between parties on that rate. This case analysis is maintained by casestatus.in based on publicly available court records.
Case Summary: 88/2025 (PGVCL v. Solanki Chanabhai Madhabhai) The court partially allowed PGVCL's electricity recovery suit against the respondent. The court found the respondent liable for unpaid electricity dues of ₹8,433.04 with 6% annual interest from the billing date until payment, rejecting PGVCL's claim for 16% interest due to lack of contractual agreement between parties on that rate. This case analysis is maintained by casestatus.in based on publicly available court records.