M/S RAHUL CONSTRUCTIONS vs SHRI BASAVARAJU S. SECRETARY — CONT/942/2025
Next hearing: 15th May 2026.
CNR: CGHC010254742025
Filing Number
CONT/15532/2025
Filing Date
20-Jun-2025
Registration No
CONT/942/2025
Registration Date
02-Jul-2025
Judge
Hon'ble Shri Justice Naresh Kumar Chandravanshi
Coram
Hon'ble Shri Justice Naresh Kumar Chandravanshi
Bench Type
Single Bench
Category
CONTEMPT OF COURT MATTERS ( 16 )
Sub-Category
OTHER CIVIL CONTEMPT MATTERS ( 1603 )
Judicial Branch
Civil Section
Last updated 17-May-2026
Petitioner(s)
-
1.M/S RAHUL CONSTRUCTIONS
Adv. Surya Kawalkar Dangi,PRIYANKA BAJPAI,PRIYANKA BAJPAI, ,Saurabh Dangi,Aditi Singhvi,AISHWARY PRASAD,SAJAL KUMAR GUPTA,PALAK DWIVEDI,CHANDRASHEKHAR BAJPAI,CHANDRASHEKHAR BAJPAI
Respondent(s)
-
1.SHRI BASAVARAJU S. SECRETARY
-
2.Shri Remejeus Ekka
Adv. DHARMESH SRIVASTAVA
-
3.Shri Amresh Singh
Adv. MATEEN SIDDIQUI,SANDEEP SINGH NARENDRA MEHAR waquar naiyer ABHYUDAY TRIPATHI DANISH AHMAD SIDDIQUI ZAINAB MUSTAFA VANAK APOORVA PANDEY SIBASISH MISHRA APURVA NIGAM ISHAN SALUJA RUPESH SAHU
-
4.Shri Dujram Kurre
-
5.Shri Pratik Pandey
Case History
-
15-May-2026
Next hearingPending
-
05-May-2026
Hon'ble Shri Justice Parth Prateem SahuView PDF
Summary: The case (CONT No. 942 of 2025) between M/S Rahul Constructions and Shri Basavaraju S. Secretary at the High Court of Chhattisgarh was adjourned. The respondent authorities conducted a spot inspection and prepared a panchnama on 21.04.2026, but the petitioner refused to sign it. The respondent undertook to file an affidavit regarding this incident and submit a decision on the petitioner's claim regarding Work Order No. 915 by the next hearing date. This case analysis is maintained by casestatus.in based on publicly available court records.
-
10-Apr-2026
Hon'ble Shri Justice Parth Prateem SahuView PDF
-
24-Feb-2026
Hon'ble Shri Justice Parth Prateem SahuView PDF
-
16-Feb-2026
Fresh Matters
Hon'ble Shri Justice Parth Prateem Sahu
-
19-Jan-2026
Hon'ble Shri Justice Parth Prateem SahuView PDF
-
04-Jul-2025
Hon'ble Shri Justice Ravindra Kumar AgrawalView PDF
-
04-Jul-2025
First hearing
Initial hearing scheduled
-
20-Jun-2025
Case filed
Registration No. CONT/942/2025
Summary: The case (CONT No. 942 of 2025) between M/S Rahul Constructions and Shri Basavaraju S. Secretary at the High Court of Chhattisgarh was adjourned. The respondent authorities conducted a spot inspection and prepared a panchnama on 21.04.2026, but the petitioner refused to sign it. The respondent undertook to file an affidavit regarding this incident and submit a decision on the petitioner's claim regarding Work Order No. 915 by the next hearing date. This case analysis is maintained by casestatus.in based on publicly available court records.