MAHARASHTRA KRISHNA VALLEY CORPORATION THROUGH ITS EXECUTIVE ENGINEER vs SADASHIV GANU UBHE (DECEASED) BY LRS. 1.1 TO 1.5 1. — HCBM10476422025

Case under Land Acquisition Act Section 54. Next hearing: 01st April 2026.

Next hearing 01-Apr-2026

CNR: HCBM010476422025

Filing Number

FA/30126/2025

Filing Date

08-Sep-2025

Judge

Hon'ble Shri Justice Somasekhar Sundaresan

Coram

Hon'ble Shri Justice Somasekhar Sundaresan

Bench Type

Single

Category

FIRST APPEAL ( 53 )

Sub-Category

Land Aquisition - Single Bench ( 2 )

Judicial Branch

Civil

Last updated 02-May-2026

Acts & Sections

Land Acquisition Act Section 54

Petitioner(s)

  1. 1.MAHARASHTRA KRISHNA VALLEY CORPORATION THROUGH ITS EXECUTIVE ENGINEER

    Adv. NITIN GAWARE PATIL

Respondent(s)

  1. 1.SADASHIV GANU UBHE (DECEASED) BY LRS. 1.1 TO 1.5 1.

  2. 2.PUNDLIK SADASHIV UBHE

    Adv. P H Potnis1.

  3. 3.PANDURANG SADASHIV UBHE

    Adv. P H Potnis1.

  4. 4.ASHA BALU KANGUDE

    Adv. P H Potnis1.

  5. 5.MAYA RAJENDRA BHIKULE

    Adv. P H Potnis1.

  6. 6.LAXMIBAI SADASHIV UBHE (DECEASED)

  7. 7.THE LAND ACQUISITION OFFICER NO.6,

  8. 8.THE COLLECTOR

Case History

  1. 01-Apr-2026

    Next hearingPending

  2. 07-Apr-2026

    At 3.00 P.M.

    Hon'ble Shri Justice Somasekhar Sundaresan

  3. 01-Apr-2026

    Hon'ble Shri Justice Somasekhar SundaresanView PDF

  4. 30-Mar-2026

    -For Order- First Appeal

    Hon'ble Shri Justice Somasekhar Sundaresan

  5. 25-Mar-2026

    Hon'ble Shri Justice Somasekhar SundaresanView PDF

    The High Court of Judicature at Bombay adjourned multiple consolidated First Appeals and interim applications involving Maharashtra Krishna Valley Development Corporation versus Balkrishna Hari Ubhe and others to April 1, 2026. No substantive orders on the merits were issued; the case was simply stood over for the next hearing date. This case analysis is maintained by casestatus.in based on publicly available court records.

  6. 09-Mar-2026

    For Circulation

    Hon'ble Shri Justice Somasekhar Sundaresan

  7. 12-Nov-2025

    For Orders (Due Matters)

    Hon'ble Ms. Justice Gauri Godse

  8. 07-Oct-2025

    Hon'ble Ms. Justice Gauri GodseView PDF

  9. 07-Oct-2025

    Fresh Admission

    Hon'ble Ms. Justice Gauri Godse

  10. 15-Sep-2025

    Hon'ble Ms. Justice Gauri GodseView PDF

  11. 15-Sep-2025

    First hearing

    Initial hearing scheduled

  12. 08-Sep-2025

    Case filed

casestatus.in Summary

The High Court of Judicature at Bombay adjourned multiple consolidated First Appeals and interim applications involving Maharashtra Krishna Valley Development Corporation versus Balkrishna Hari Ubhe and others to April 1, 2026. No substantive orders on the merits were issued; the case was simply stood over for the next hearing date. This case analysis is maintained by casestatus.in based on publicly available court records.