MS BHATT AND THAPLIYAL ENGINEERING vs UTTARAKHAND RURAL ROAD DEVELOPMENT AGENCY — WPMB/484/2026
Case under Under Article 226 of the Constituion of India Section 226. Next hearing: 15th June 2026.
CNR: UKHC010101092026
Next Hearing
15th June 2026
Filing Number
WPMB/5280/2026
Filing Date
08-06-2026
Registration No
WPMB/484/2026
Registration Date
08-06-2026
Judge
Hon'ble Shri Justice Manoj Kumar Gupta , Hon'ble Mr. Justice Subhash Upadhyay
Coram
Hon'ble Shri Justice Manoj Kumar Gupta , Hon'ble Mr. Justice Subhash Upadhyay
Bench Type
Division Bench
Category
MISC WRIT PETITION ( 2 )
Sub-Category
WRIT PETITION RELATING TO CONTRACT/TENDER MATTER ( 23 )
Judicial Branch
ALL SECTIONS (CIVIL AND CRIMINAL)
Acts & Sections
Petitioner(s)
MS BHATT AND THAPLIYAL ENGINEERING
Adv. VIKAS BAHUGUNA,YASH BISHT,YASH BISHT, ,YASH BISHT
Respondent(s)
UTTARAKHAND RURAL ROAD DEVELOPMENT AGENCY
CHIEF ENGINEER
Adv. S S CHAUHAN
BID EVALUATION COMMITTEE
Adv. S S CHAUHAN
A K BUILDSOLUTION PVT LTD
Adv. S S CHAUHAN
M/S JPH INFRA THROUGH CHIEF ENGINEER
Adv. S S CHAUHAN
Hearing History
Judge: Hon'ble Shri Justice Manoj Kumar Gupta , Hon'ble Mr. Justice Subhash Upadhyay
FRESH CASES FOR ADMISSION -3
FRESH CASES FOR ADMISSION -3
FRESH CASES FOR ADMISSION -3
| Date | Purpose |
|---|---|
| 10-06-2026 | FRESH CASES FOR ADMISSION -3 |
| 15-06-2026 | FRESH CASES FOR ADMISSION -3 |
| 11-06-2026 | FRESH CASES FOR ADMISSION -3 |
Orders
Case Summary: WPMB/484/2026 In this writ petition by M/s Bhatt and Thapliyal Engineering against Uttarakhand Rural Road Development Agency, the court adjourned the matter to 15.06.2026 as fresh. The respondent stated that financial bids were under evaluation based on objections filed by bidders, with a decision to be rendered on the same day and financial bids to be opened thereafter. The court directed that the department's decision on the petitioner's objections be placed on record. This case analysis is maintained by casestatus.in based on publicly available court records.
Case Summary: WPMB/484/2026 In this writ petition by M/s Bhatt and Thapliyal Engineering against Uttarakhand Rural Road Development Agency, the court adjourned the matter to 15.06.2026 as fresh. The respondent stated that financial bids were under evaluation based on objections filed by bidders, with a decision to be rendered on the same day and financial bids to be opened thereafter. The court directed that the department's decision on the petitioner's objections be placed on record. This case analysis is maintained by casestatus.in based on publicly available court records.