SANJAY KUMAR vs MUKHYA NAGAR ADHIKARI NAGAR NIGAM HARIDWAR Advocate - SANDEEP KOTHARI — WPMS/1595/2026

Case under Under Article 226 of the Constituion of India Section 226. Disposed: Contested--DISPOSED on 30th May 2026.

Case disposed

CNR: UKHC010091462026

Filing Number

WPMS/4761/2026

Filing Date

27-May-2026

Registration No

WPMS/1595/2026

Registration Date

27-May-2026

Judge

Hon'ble Mr. Justice Pankaj Purohit

Coram

Hon'ble Mr. Justice Pankaj Purohit

Bench Type

Single Bench

Category

MISC WRIT PETITION ( 2 )

Sub-Category

MISC MATTERS ( 47 )

Judicial Branch

ALL SECTIONS (CIVIL AND CRIMINAL)

Decision Date

30-May-2026

Nature of Disposal

Contested--DISPOSED

Last updated 01-Jun-2026

Acts & Sections

Under Article 226 of the Constituion of India Section 226

Petitioner(s)

  1. 1.SANJAY KUMAR

    Adv. ARVIND KUMAR SHARMA

Respondent(s)

  1. 1.MUKHYA NAGAR ADHIKARI NAGAR NIGAM HARIDWAR Advocate - SANDEEP KOTHARI

  2. 2.EXECUTIVE ENGINEER

    Adv. SANDEEP KOTHARI

Case History

  1. Case disposedDisposed

  2. 30-May-2026

    Hon'ble Mr. Justice Pankaj PurohitView PDF

    Case Summary: WPMS/1595/2026 Case: Sanjay Kumar v. Mukhya Nagar Adhikari Nagar Nigam Haridwar (High Court of Uttarakhand, 30 May 2026) Decision: The court disposed of multiple writ petitions filed by contractors claiming unpaid dues for completed civil works executed for Nagar Nigam Haridwar during 2024-2025. Rather than granting a mandamus for immediate payment with 18% interest as sought, the court allowed petitioners to submit fresh representations within two weeks, directing the respondent municipality to consider and decide these within eight weeks by passing reasoned orders in accordance with law. This case analysis is maintained by casestatus.in based on publicly available court records.

  3. 30-May-2026

    Fresh Cases For Admission -3

    Hon'ble Mr. Justice Pankaj Purohit

  4. 27-May-2026

    Case filed

    Registration No. WPMS/1595/2026

casestatus.in Summary

Case Summary: WPMS/1595/2026 Case: Sanjay Kumar v. Mukhya Nagar Adhikari Nagar Nigam Haridwar (High Court of Uttarakhand, 30 May 2026) Decision: The court disposed of multiple writ petitions filed by contractors claiming unpaid dues for completed civil works executed for Nagar Nigam Haridwar during 2024-2025. Rather than granting a mandamus for immediate payment with 18% interest as sought, the court allowed petitioners to submit fresh representations within two weeks, directing the respondent municipality to consider and decide these within eight weeks by passing reasoned orders in accordance with law. This case analysis is maintained by casestatus.in based on publicly available court records.