HEM KUMAR SANPREET SINGH AJMANI, BHAVYA PRATAP SINGH RAUTELA, AMITOZ KAUR, vs UTTARAKHAND POWER CORPORATION LIMITED Advocate - DHARMENDRA BARTHWAL — WPSB/279/2026

Case under Under Article 226 of the Constituion of India Section 226. Disposed: Contested--DISPOSED on 17th June 2026.

Case disposed

CNR: UKHC010077162026

Filing Number

WPMS/4021/2026

Filing Date

08-May-2026

Registration No

WPSB/279/2026

Registration Date

08-May-2026

Judge

Hon'ble Shri Justice Manoj Kumar Gupta , Hon'ble Mr. Justice Subhash Upadhyay

Coram

Hon'ble Shri Justice Manoj Kumar Gupta , Hon'ble Mr. Justice Subhash Upadhyay

Bench Type

Single Bench

Category

SERVICE WRIT PETITION ( 1 )

Sub-Category

PROMOTION ( 10 )

Judicial Branch

ALL SECTIONS (CIVIL AND CRIMINAL)

Decision Date

17-Jun-2026

Nature of Disposal

Contested--DISPOSED

Last updated 18-Jun-2026

Acts & Sections

Under Article 226 of the Constituion of India Section 226

Petitioner(s)

  1. 1.HEM KUMAR SANPREET SINGH AJMANI, BHAVYA PRATAP SINGH RAUTELA, AMITOZ KAUR,

Respondent(s)

  1. 1.UTTARAKHAND POWER CORPORATION LIMITED Advocate - DHARMENDRA BARTHWAL

  2. 2.EXECUTIVE ENGINEER

Case History

  1. Case disposedDisposed

  2. 17-Jun-2026

    Hon'ble Shri Justice Manoj Kumar Gupta,Hon'ble Mr. Justice Subhash UpadhyayView PDF

    Case Summary: WPSB/279/2026 The Uttarakhand High Court disposed of the petition allowing the petitioner's grievance that promotional benefits were withheld despite his promotion from Junior Engineer to Assistant Engineer (June 2023) due to an outstanding miscellaneous advance. The court directed Uttarakhand Power Corporation to decide the petitioner's representation with a fresh submission within six weeks by a reasoned order. This case analysis is maintained by casestatus.in based on publicly available court records.

  3. 03-Jun-2026

    Fresh Cases As Defective -236

    Registrar (Judicial)

  4. 08-May-2026

    Case filed

    Registration No. WPSB/279/2026

casestatus.in Summary

Case Summary: WPSB/279/2026 The Uttarakhand High Court disposed of the petition allowing the petitioner's grievance that promotional benefits were withheld despite his promotion from Junior Engineer to Assistant Engineer (June 2023) due to an outstanding miscellaneous advance. The court directed Uttarakhand Power Corporation to decide the petitioner's representation with a fresh submission within six weeks by a reasoned order. This case analysis is maintained by casestatus.in based on publicly available court records.