THE EXECUTIVE ENGINEER vs SHASHIKALA — C.A. No. 3670/2026

Case under Land Acquisition and Requisition : Compensation for Land Acquisition Section XII-B. Status: Disposed.

Disposed

CNR: SCIN010034242026

Filing Date

17-Jan-2026

Registration No

C.A. No. 3670/2026

Diary Number

3424/2026

Order Date

16-Mar-2026

Document Type

ROP - of Main Case

Disposal Type

Leave Granted & Allowed

Last updated 06-Jun-2026

Acts & Sections

Land Acquisition and Requisition : Compensation for land acquisition Section XII-B

Petitioner(s)

  1. 1.THE EXECUTIVE ENGINEER

    Adv. HETU ARORA SETHI

Respondent(s)

  1. 1.SHASHIKALA

Case History

  1. Case disposedDisposed

  2. 16-Mar-2026

    ROP - of Main CaseView PDF

  3. 16-Mar-2026

    Fixed Date by Court

    Hon'ble Mr. Justice M.M. Sundresh and Hon'ble Mr. Justice Nongmeikapam Kotiswar Singh

  4. 09-Feb-2026

    ROP - of Main CaseView PDF

  5. 09-Feb-2026

    Fixed Date by Court

    Hon'ble Mr. Justice J.B. Pardiwala and Hon'ble Mr. Justice K.V. Viswanathan

  6. 27-Jan-2026

    ROP - of Main CaseView PDF

  7. 27-Jan-2026

    First hearing

    Initial hearing scheduled

  8. 17-Jan-2026

    Case filed

    Registration No. C.A. No. 3670/2026

casestatus.in Summary

Summary: The Supreme Court heard a Special Leave Petition (SLP) filed by The Executive Engineer against Shashikala & Anr. on 27-01-2026. The petitioner's counsel requested that the matter be deferred pending judgment in a related case (Deputy Commissioner vs. S.V. Global Mill Limited, SLP(C) No.215/2023) that was reserved on 10-12-2025. The Court granted the request and adjourned the matter to 09-02-2026 for further proceedings. This case analysis is maintained by casestatus.in based on publicly available court records.