CCECC-TPL JV vs GUJARAT METRO RAIL CORPORATION LIMITED — SLP(C) No. 17416/2026
Case under Arbitration Law and Other Alternative Dispute Resolution : Challenge to Arbitral Award, Matters Relating to Execution Under Section 36, Under Section 34/Section 37 of the Arbitration & Conciliation Act, 1996 and Challenges to Arbitral Award Under Arbitration Act, 1940 Section III-B. Status: Disposed.
CNR: SCIN010288352026
Filing Date
09-May-2026
Registration No
SLP(C) No. 17416/2026
Diary Number
28835/2026
Order Date
19-May-2026
Document Type
ROP - of Main Case
Disposal Type
Disposed Off
Last updated 29-Jun-2026
Acts & Sections
Petitioner(s)
-
1.CCECC-TPL JV
Adv. SRISHTI KUMAR
Respondent(s)
-
1.GUJARAT METRO RAIL CORPORATION LIMITED
Case History
-
Case disposedDisposed
-
19-May-2026
ROP - of Main CaseView PDF
-
19-May-2026
Mention Memo
Hon'ble Mr. Justice Pamidighantam Sri Narasimha and Hon'ble Mr. Justice Alok Aradhe
-
09-May-2026
Case filed
Registration No. SLP(C) No. 17416/2026
Case Summary: SLP(C) No. 017416/2026 Outcome: The Supreme Court disposed of CCECC-TPL JV's Special Leave Petition, affirming the High Court's interim arrangement requiring GMRCL to keep Rs. 108 crores (the arbitral award amount) in an interest-bearing fixed deposit pending disposal of Section 34 objections by July 31, 2026. The Court rejected the petitioner's request for withdrawal of funds during the objection period. Next Steps: If Section 34 objections are not taken up by July 31, 2026 or thereafter, petitioner may approach the High Court for modification, which will decide on case merits without expressing any opinion on the substantive matter. This case analysis is maintained by casestatus.in based on publicly available court records.