KARNATAKA POWER TRANSMISSION CORPORATION LIMITED THROUGH ITS G.M.(TECHNICAL) vs JSW ENERGY LIMITED — C.A. No. 8714/2022
Case under Section XII-B. Status: DISPOSED.
CNR: SCIN010186072004
Filing Date
25-Aug-2004
Registration No
C.A. No. 8714/2022
Diary Number
18607/2004
Order Date
22-Nov-2022
Document Type
ROP - of Main Case
Neutral Citation
2022 INSC 1219
Disposal Type
Partly Allowed
Data as of 29-Jun-2026
Acts & Sections
Petitioner(s)
KARNATAKA POWER TRANSMISSION CORPORATION LIMITED THROUGH ITS G.M.(TECHNICAL)
Adv. RAGHAVENDRA S. SRIVATSA (Dead / Retired / Elevated)
Respondent(s)
JSW ENERGY LIMITED
Adv. V. N. RAGHUPATHY RAHUL PRASANNA DAVE CYRIL AMARCHAND MANGALDAS AOR
Hearing History
Judge: HON'BLE MR. JUSTICE K.M. JOSEPH, HON'BLE MR. JUSTICE AJAY RASTOGI, HON'BLE MR. JUSTICE ANIRUDDHA BOSE, HON'BLE MR. JUSTICE HRISHIKESH ROY and HON'BLE MR. JUSTICE C.T. RAVIKUMAR
Fixed Date by Court
Fixed Date by Court
Next Week / Week Commencing / C.O.Week
Next Week / Week Commencing / C.O.Week
Next Week / Week Commencing / C.O.Week
| Date | Purpose |
|---|---|
| 22-Nov-2022 | Fixed Date by Court |
| 27-Sep-2022 | Fixed Date by Court |
| 22-Sep-2022 | Next Week / Week Commencing / C.O.Week |
| 21-Sep-2022 | Next Week / Week Commencing / C.O.Week |
| 20-Sep-2022 | Next Week / Week Commencing / C.O.Week |
Orders
Case Summary: CA No. 008714/2022 On 22-11-2022, the Supreme Court partly allowed Karnataka Power Transmission Corporation Limited's appeal against JSW Energy Limited, finding no contract was concluded under Section 27(2) of the relevant Act. The Court remanded the case to the High Court to reconsider two points and directed JSW Energy to pay Rs. 50 crores within eight weeks, with further liability dependent on the High Court's decision. Each party bears its own costs. This case analysis is maintained by casestatus.in based on publicly available court records.