KARNATAKA ROAD DEVELOPMENT CORPORATION LIMITED vs M/S. DRN INFRASTRUCTURE PVT. LTD. — R.P.(C) No. 9630/2026

Case under Arbitration Law and Other Alternative Dispute Resolution : Challenge to Arbitral Award, Matters Relating to Execution Under Section 36, Under Section 34/Section 37 of the Arbitration & Conciliation Act, 1996 and Challenges to Arbitral Award Under Arbitration Act, 1940 Section IV-A. Status: DISPOSED.

CNR: SCIN010182632026

DISPOSED

Filing Date

24-Mar-2026

Registration No

R.P.(C) No. 9630/2026

Diary Number

18263/2026

Order Date

06-May-2026

Document Type

ROP - of Main Case

Disposal Type

Delay Condoned and matter dismissed(including all pending Ias)

Data as of 20-Jun-2026

Acts & Sections

Arbitration Law and Other Alternative Dispute Resolution : Challenge to arbitral award, matters relating to execution under Section 36, under Section 34/Section 37 of the Arbitration & Conciliation Act, 1996 and challenges to arbitral award under Arbitration Act, 1940 Section IV-A

Petitioner(s)

KARNATAKA ROAD DEVELOPMENT CORPORATION LIMITED

Adv. D. L. CHIDANANDA

Respondent(s)

M/S. DRN INFRASTRUCTURE PVT. LTD.

Hearing History

Judge: HON'BLE MR. JUSTICE J.K. MAHESHWARI and HON'BLE MR. JUSTICE ATUL S. CHANDURKAR

06-May-2026

FRESH

Orders

View Full Judgment
casestatus.in Summary

Summary: The Supreme Court dismissed the review petitions filed by Karnataka Road Development Corporation Limited against M/S. DRN Infrastructure Pvt. Ltd., finding no grounds for review of the order dated 19.01.2026. The Court condoned the delay in filing and disposed of all pending applications. The matter concluded on 06.05.2026 with finality. This case analysis is maintained by casestatus.in based on publicly available court records.

Browse Related Cases

More from this court

Supreme Court of India All courts →

Explore other courts