CHARAN SINGH vs LAND ACQUISITION COLLECTOR LAND ACQUISITION INDUSTRIES DEPARTMENT — C.A. No. 9067 - 9082/2013
Case under Section IV. Status: Disposed.
CNR: SCIN010144912011
Filing Date
02-May-2011
Registration No
C.A. No. 9067 - 9082/2013
Diary Number
14491/2011
Order Date
27-Jun-2018
Document Type
ROP - of Main Case
Disposal Type
Allowed
Last updated 05-Jul-2026
Acts & Sections
Petitioner(s)
-
1.CHARAN SINGH
Adv. MRS. VIPIN GUPTA
Respondent(s)
-
1.LAND ACQUISITION COLLECTOR LAND ACQUISITION INDUSTRIES DEPARTMENT
Adv. B. KRISHNA PRASAD UTTARA BABBAR (Dead / Retired / Elevated)
Case History
-
Case disposedDisposed
-
27-Jun-2018
ROP - of Main CaseView PDF
-
27-Jun-2018
Ordinary
Hon'ble Mr. Justice Arun Mishra and Hon'ble Mr. Justice Sanjay Kishan Kaul
-
01-May-2017
ROPView PDF
-
01-May-2017
ROPView PDF
-
03-Apr-2017
ROPView PDF
-
03-Apr-2017
Office ReportView PDF
-
03-Apr-2017
ROPView PDF
-
28-Oct-2016
ROPView PDF
-
28-Oct-2016
Office ReportView PDF
-
28-Oct-2016
ROPView PDF
-
30-Sep-2016
ROPView PDF
-
30-Sep-2016
Office ReportView PDF
-
30-Sep-2016
ROPView PDF
-
22-Jul-2016
ROPView PDF
-
22-Jul-2016
Office ReportView PDF
-
22-Jul-2016
ROPView PDF
-
29-Apr-2016
ROPView PDF
-
29-Apr-2016
Office ReportView PDF
-
29-Apr-2016
ROPView PDF
-
10-Mar-2016
ROPView PDF
-
10-Mar-2016
ROPView PDF
-
14-Jan-2016
ROPView PDF
-
14-Jan-2016
Office ReportView PDF
-
14-Jan-2016
ROPView PDF
-
02-Sep-2015
ROP - of Main CaseView PDF
-
02-Sep-2015
ROP - of Main CaseView PDF
-
28-Aug-2015
ROPView PDF
-
28-Aug-2015
ROPView PDF
-
21-Aug-2015
Office ReportView PDF
-
21-Aug-2015
ROPView PDF
-
10-Jan-2014
ROPView PDF
-
19-Nov-2013
ROPView PDF
-
30-Sep-2013
ROP - of Main CaseView PDF
-
23-Sep-2013
ROPView PDF
-
05-Jul-2013
ROP - of Main CaseView PDF
-
03-May-2013
ROPView PDF
-
22-Apr-2013
ROP - of Main CaseView PDF
-
03-Apr-2013
ROPView PDF
-
03-Apr-2013
ROPView PDF
-
18-Mar-2013
ROP - of Main CaseView PDF
-
06-Feb-2013
ROPView PDF
-
15-Oct-2012
ROP - of Main CaseView PDF
-
08-Oct-2012
ROPView PDF
-
06-Sep-2012
ROPView PDF
-
05-Sep-2012
ROP - of Main CaseView PDF
-
23-Jul-2012
ROP - of Main CaseView PDF
-
04-May-2012
ROPView PDF
-
07-Jul-2011
ROP - of Main CaseView PDF
-
02-May-2011
Case filed
Registration No. C.A. No. 9067 - 9082/2013
Case Summary: Charan Singh v. Land Acquisition Collector Outcome: The Supreme Court allowed the appeals and set aside the High Court's judgment. The Court awarded land compensation uniformly at Rs. 46,829 per acre with statutory benefits for land acquired at Kapurthala for the Integral Coach Factory, finding the High Court erred in discarding comparable sale evidence executed before the notification date. Next Steps: Compensation to be paid within three months if not already disbursed. No order regarding costs. This case analysis is maintained by casestatus.in based on publicly available court records.
Explore other courts