ELSAMEX-TWS-SNC JOINT VENTURE THROUGH DIRECTOR PROJECTS SRI B. SUNIL SHETTY vs NATIONAL HIGHWAYS AUTHORITY OF INDIA THROUGH GENERAL MANAGER C.K.II — C.A. No. 6618/2009
Case under Section XIV-A. Status: DISPOSED.
CNR: SCIN010137522008
Filing Date
08-May-2008
Registration No
C.A. No. 6618/2009
Diary Number
13752/2008
Order Date
07-Aug-2019
Document Type
ROP - of Main Case
Disposal Type
Dismissed
Data as of 03-Jul-2026
Acts & Sections
Petitioner(s)
ELSAMEX-TWS-SNC JOINT VENTURE THROUGH DIRECTOR PROJECTS SRI B. SUNIL SHETTY
Adv. MRS. VIPIN GUPTA
Respondent(s)
NATIONAL HIGHWAYS AUTHORITY OF INDIA THROUGH GENERAL MANAGER C.K.II
Adv. M. V. KINI & ASSOCIATES
Hearing History
Judge: HON'BLE MR. JUSTICE N.V. RAMANA, HON'BLE MR. JUSTICE MOHAN M. SHANTANAGOUDAR and HON'BLE MR. JUSTICE AJAY RASTOGI
Fixed Date by Court
Ordinary
| Date | Purpose |
|---|---|
| 07-Aug-2019 | Fixed Date by Court |
| 20-Jul-2017 | Ordinary |
Orders
Summary of C.A. No. 006618/2009 The Supreme Court disposed of ELSAMEX-TWS-SNC's appeal against NHAI regarding disputed bank guarantees. The court continued interim protection for bank guarantees (Serial Nos. 2-5) related to mobilization/equipment advances until the High Court disposes of OMP(Comm)No.48/2019, requiring these guarantees be kept alive and renewed. Bank guarantees for performance security and discretionary advances (Serial Nos. 1, 10-24) were already encashed following a 2008 order. This case analysis is maintained by casestatus.in based on publicly available court records.
Browse Related Cases
Explore other courts