NIMBUS COMMUNICATIONS LTD. vs BOARD OF CONTROL FOR CRICKET IN IND. — SLP(C) No. 9314/2012
Case under Section IX. Status: Disposed.
CNR: SCIN010090672012
Filing Date
15-Mar-2012
Registration No
SLP(C) No. 9314/2012
Diary Number
9067/2012
Order Date
04-Apr-2012
Document Type
ROP - of Main Case
Disposal Type
Dismissed
Last updated 05-Jul-2026
Acts & Sections
Petitioner(s)
-
1.NIMBUS COMMUNICATIONS LTD.
Adv. JAYANT MOHAN
Respondent(s)
-
1.BOARD OF CONTROL FOR CRICKET IN IND.
Adv. KARANJAWALA & CO.
Case History
Case Summary: Nimbus Communications Ltd. v. BCCI On 04/04/2012, the Supreme Court dismissed Nimbus Communications' special leave petition challenging the Bombay High Court's ad-interim order in an arbitration proceeding under Section 9 of the Arbitration and Conciliation Act, 1996. The Court directed the High Court's Single Judge to dispose of the pending Notice of Motion within four weeks, instructing that the decision be made independently without being influenced by observations in the ad-interim order. This case analysis is maintained by casestatus.in based on publicly available court records.