MUN.CORP.OF DELHI vs M/S NITTY CONSTRUC.CO.LTD. — SLP(C) No. 16088/2012
Case under Section I-B. Status: Disposed.
CNR: SCIN010078912012
Filing Date
03-Mar-2012
Registration No
SLP(C) No. 16088/2012
Diary Number
7891/2012
Order Date
05-Aug-2013
Document Type
ROP - of Main Case
Disposal Type
Dismissed
Last updated 05-Jul-2026
Acts & Sections
Petitioner(s)
-
1.MUN.CORP.OF DELHI
Adv. P. PARMESWARAN
Respondent(s)
-
1.M/S NITTY CONSTRUC.CO.LTD.
Case History
Summary: On August 5, 2013, the Supreme Court heard four consolidated special leave petitions (SLP(C) Nos. 16088, 16089, 16092, and 16095 of 2012) filed by the Municipal Corporation of Delhi against M/S Nitty Construction Co. Ltd., all containing prayers for interim relief. After hearing counsel for both parties, the Court dismissed all the special leave petitions. This case analysis is maintained by casestatus.in based on publicly available court records.