THE ASSAM STATE ELECTRICITY BOARD REPRESENTED BY ITS CHAIRMAN vs BUILDWORTH PVT. LTD. REPRESENTED BY ITS DIRECTOR SHRI PRADIP KUMAR SINGH — C.A. No. 484/2008

Case under Section XIV-A. Status: Disposed.

Disposed

CNR: SCIN010022602007

Filing Date

19-Jan-2007

Registration No

C.A. No. 484/2008

Diary Number

2260/2007

Order Date

04-Jul-2017

Document Type

Judgement - of Main Case

Neutral Citation

2017 INSC 587

Disposal Type

Dismissed

Last updated 17-Jun-2026

Acts & Sections

Section XIV-A

Petitioner(s)

  1. 1.THE ASSAM STATE ELECTRICITY BOARD REPRESENTED BY ITS CHAIRMAN

    Adv. SNEHA KALITA

Respondent(s)

  1. 1.BUILDWORTH PVT. LTD. REPRESENTED BY ITS DIRECTOR SHRI PRADIP KUMAR SINGH

    Adv. RAJIV MEHTA

Case History

  1. Case disposedDisposed

  2. 04-Jul-2017

    Judgement - of Main CaseView PDF

  3. 04-Jul-2017

    Fixed Date by Court

    Hon'ble Mr. Justice D.Y. Chandrachud

  4. 20-Apr-2017

    ROP - of Main CaseView PDF

  5. 20-Apr-2017

    ROP - of Main CaseView PDF

  6. 19-Apr-2017

    Office Report - of Main CaseView PDF

  7. 05-Nov-2014
  8. 05-Nov-2014

    Office ReportView PDF

  9. 05-Nov-2014
  10. 20-Aug-2014

    Office ReportView PDF

  11. 20-Aug-2014
  12. 29-Apr-2014

    ROP - of Main CaseView PDF

  13. 06-Mar-2014

    Office Report - of Main CaseView PDF

  14. 06-Mar-2014

    ROP - of Main CaseView PDF

  15. 27-Jan-2014

    ROP - of Main CaseView PDF

  16. 16-Jan-2013

    ROP - of Main CaseView PDF

  17. 16-Apr-2012

    ROP - of Main CaseView PDF

  18. 03-May-2011

    ROP - of Main CaseView PDF

  19. 07-Dec-2007

    ROP - of Main CaseView PDF

  20. 10-Sep-2007

    ROP - of Main CaseView PDF

  21. 02-Aug-2007

    ROP - of Main CaseView PDF

  22. 02-Apr-2007

    ROP - of Main CaseView PDF

  23. 05-Feb-2007

    ROP - of Main CaseView PDF

  24. 19-Jan-2007

    Case filed

    Registration No. C.A. No. 484/2008

  25. [ 2017 INSC 587 ]

    Judgement - of Main CaseView PDF

casestatus.in Summary

Case Summary: Assam State Electricity Board v. Buildworth Pvt. Ltd. Court Decision: The Supreme Court dismissed the Board's appeal and allowed Buildworth's appeals. The arbitrator's awards for price escalation and idling charges were upheld. Interest was awarded from 20 April 1987 to 31 December 1997 and thereafter at 12% p.a. (reduced from the awarded 18% p.a.). Key Reasoning: The Court held that price escalation applies beyond the scheduled contract period when work extends due to circumstances beyond the contractor's control, and that arbitrators can award interest on damages under the Interest Act, 1978, even for pre-reference periods when notice is given. This case analysis is maintained by casestatus.in based on publicly available court records.