M/S BSCPL INFRASTRUCTURE LTD vs STATE OF CHHATTISGARH — SLP(C) No. 4121 - 4122/2024

Case under Mines Minerals, Mining Leases : Grant/renewal And/or Cancellation of Reconnaissance Permits, Prospecting Licenses And/or Mining Leases, Payment of Royalty Under Any Central or State Statute Section IV-C. Status: Pending.

Pending

CNR: SCIN010005182024

Filing Date

03-Jan-2024

Registration No

SLP(C) No. 4121 - 4122/2024

Diary Number

518/2024

Order Date

25-Feb-2025

Document Type

ROP - of Main Case

Last updated 28-May-2026

Acts & Sections

Mines Minerals, Mining leases : Grant/renewal and/or cancellation of reconnaissance permits, prospecting licenses and/or mining leases, payment of royalty under any Central or State statute Section IV-C

Petitioner(s)

  1. 1.M/S BSCPL INFRASTRUCTURE LTD

    Adv. KIRTI RENU MISHRA

Respondent(s)

  1. 1.STATE OF CHHATTISGARH

    Adv. APOORV SHUKLA[R-1] APOORV SHUKLA[R-2] APOORV SHUKLA[R-3]

Case History

  1. 05-Aug-2025

    Fixed Date by Court

    Hon'ble Mr. Justice Dipankar Datta and Hon'ble Mr. Justice Augustine George Masih

  2. 25-Feb-2025

    ROP - of Main CaseView PDF

  3. 25-Feb-2025

    Fixed Date by Court

    Hon'ble Mr. Justice Abhay S. Oka and Hon'ble Mr. Justice Ujjal Bhuyan

  4. 10-Sep-2024

    ROP - of Main CaseView PDF

  5. 10-Sep-2024

    Fixed Date by Court

    Hon'ble Mr. Justice Abhay S. Oka and Hon'ble Mr. Justice Augustine George Masih

  6. 26-Apr-2024

    ROP - of Main CaseView PDF

  7. 26-Apr-2024

    Fixed Date by Court

    Hon'ble Mr. Justice Abhay S. Oka and Hon'ble Mr. Justice Ujjal Bhuyan

  8. 15-Mar-2024

    ROP - of Main CaseView PDF

  9. 15-Mar-2024

    Fixed Date by Court

    Hon'ble Mr. Justice Abhay S. Oka and Hon'ble Mr. Justice Ujjal Bhuyan

  10. 05-Feb-2024

    ROP - of Main CaseView PDF

  11. 05-Feb-2024

    First hearing

    Initial hearing scheduled

  12. 03-Jan-2024

    Case filed

    Registration No. SLP(C) No. 4121 - 4122/2024

casestatus.in Summary

Case Summary: SLP(C) No. 004121-004122/2024 On 25-02-2025, the Supreme Court heard BSCPL Infrastructure Ltd's special leave petitions against High Court orders concerning a Chhattisgarh infrastructure dispute. The Court adjourned the matter to 5th August 2025 as the arguing counsel was unavailable. The Court continued earlier interim relief on condition that if the petitioner fails to deposit Rs. 5,00,000 by the 5th February 2024 deadline, the interim relief will cease. This case analysis is maintained by casestatus.in based on publicly available court records.