D.S.CONSTRUCTIONS LIMITED (NOW KNOWN AS DSC LIMITED) vs THE CHIEF ENGINEER U.P.P.W.D — SLP(C) No. 8284/2019

Case under Section XI. Status: Disposed.

Disposed

CNR: SCIN010106722019

Filing Date

25-Mar-2019

Registration No

SLP(C) No. 8284/2019

Diary Number

10672/2019

Order Date

08-Apr-2019

Document Type

ROP - of Main Case

Disposal Type

Dismissed as withdrawn

Last updated 02-Apr-2026

Acts & Sections

Section XI

Petitioner(s)

  1. 1.D.S.CONSTRUCTIONS LIMITED (NOW KNOWN AS DSC LIMITED)

    Adv. UMESH KUMAR KHAITAN

Respondent(s)

  1. 1.THE CHIEF ENGINEER U.P.P.W.D

Case History

  1. Case disposedDisposed

  2. 08-Apr-2019

    ROP - of Main CaseView PDF

  3. 08-Apr-2019

    Fresh

    Hon'ble Mr. Justice Rohinton Fali Nariman and Hon'ble Mr. Justice Vineet Saran

  4. 25-Mar-2019

    Case filed

    Registration No. SLP(C) No. 8284/2019

casestatus.in Summary

On 08-04-2019, the Supreme Court heard SLP (C) Nos. 8284/2019 and 8319/2019 filed by D.S. Construction Limited (now DSC Limited) against the Chief Engineer, U.P.P.W.D. Senior counsel for the petitioner sought permission to withdraw both Special Leave Petitions, which was granted by the bench of Justices R.F. Nariman and Vineet Saran. Both SLPs were dismissed as withdrawn, with no further directions or next date. This case analysis is maintained by casestatus.in based on publicly available court records.