Kongu Construction and Contractors vs The District Forest Officer — WP(MD)/10714/2026
Case under Others Section Others. Disposed: Contested--DISPOSED OF on 16th April 2026.
CNR: HCMD010538662026
Filing Number
WP(MD)/33031/2026
Filing Date
15-Apr-2026
Registration No
WP(MD)/10714/2026
Registration Date
15-Apr-2026
Judge
Honourable Mr Justice D.bharatha Chakravarthy
Coram
Honourable Mr Justice D.bharatha Chakravarthy
Bench Type
Single Bench
Category
Environment/Forest ( 61 )
Sub-Category
The Tamil Nadu Forest Act (V of 1882) ( 18 )
Judicial Branch
Writ Section
Decision Date
16-Apr-2026
Nature of Disposal
Contested--DISPOSED OF
Last updated 26-May-2026
Acts & Sections
Petitioner(s)
-
1.Kongu Construction and Contractors
Adv. S.DORAISWAMY,G.PERUMAL ,G.PERUMAL , ,V.ELANGOVAN,V.KANNAN,G.PERUMAL
Respondent(s)
-
1.The District Forest Officer
Adv. MR.M.LINGADURAI, LEARNED SPL.GP TAKES NOTICE FOR THE RESPONDENT 1123
Case History
-
Case disposedDisposed
-
16-Apr-2026
Honourable Mr Justice D.bharatha ChakravarthyView PDF
Case Summary: WP(MD)/10714/2026 The Madurai Bench of Madras High Court extended the work completion deadline for Kongu Construction & Contractors from 13.04.2026 to 30.04.2026 for the Slender loris conservation center project in Dindigul. The court quashed the District Forest Officer's order directing handover and imposed a final deadline with no further extensions, while directing parallel processing of bills and partial fund releases to prevent financial hardship to the contractor. This case analysis is maintained by casestatus.in based on publicly available court records.
-
16-Apr-2026
For Admission
Honourable Mr Justice D.bharatha Chakravarthy
-
15-Apr-2026
First hearing
Initial hearing scheduled
-
15-Apr-2026
Case filed
Registration No. WP(MD)/10714/2026
Case Summary: WP(MD)/10714/2026 The Madurai Bench of Madras High Court extended the work completion deadline for Kongu Construction & Contractors from 13.04.2026 to 30.04.2026 for the Slender loris conservation center project in Dindigul. The court quashed the District Forest Officer's order directing handover and imposed a final deadline with no further extensions, while directing parallel processing of bills and partial fund releases to prevent financial hardship to the contractor. This case analysis is maintained by casestatus.in based on publicly available court records.