M/s. Tamilselvan Traders vs THE TAMIL NADU POWER DISTRIBUTION — WP/23431/2026
Case under Others Section 1. Next hearing: 22nd June 2026.
CNR: HCMA011353692026
Filing Number
WP/98615/2026
Filing Date
17-Jun-2026
Registration No
WP/23431/2026
Registration Date
17-Jun-2026
Judge
Honourable Mr.Justice Mohammed Shaffiq
Coram
Honourable Mr.Justice Mohammed Shaffiq
Bench Type
Single Bench
Category
Electricity ( 56 )
Judicial Branch
WRITSECTION
Last updated 21-Jun-2026
Acts & Sections
Petitioner(s)
-
1.M/s. Tamilselvan Traders
Adv. R.S.Pandiyaraj, V.PURUSHOTHAMAN,M.Saravana Kumar,S.P.Parthasarathy
Respondent(s)
-
1.THE TAMIL NADU POWER DISTRIBUTION
-
2.THE TAMIL NADU GREEN ENERGY CORPORATION LTD.,
-
3.THE TAMIL NADU TRANSMISSION CORPORATION LTD
-
4.THE DIRECTOR / TECHNICAL
-
5.THE CHIEF ENGINEER/ NCES (FAC)
-
6.The superintending Engineer
Case History
-
22-Jun-2026
Next hearingPending
-
22-Jun-2026
For Admission
Honourable Mr.Justice Mohammed Shaffiq
-
19-Jun-2026
Honourable Mr.Justice Mohammed ShaffiqView PDF
Case Summary: WP 23431/2026 Outcome: Interim relief granted with case adjourned for final hearing. The Madras High Court granted interim directions allowing M/s. Tamilselvan Traders and M/s. Aurea Solar Pvt Ltd. to energize their solar power plants and connect to the grid on an interim basis, subject to the final outcome of the writ petitions. The court directed respondents to provide grid connectivity forthwith and adjourned the matter to 22.06.2026 for final hearing alongside related cases. The petitioners had challenged circular memos dated 27.05.2026 and 30.05.2026 that blocked solar/wind connectivity approvals despite the petitioners meeting all statutory requirements and obtaining necessary clearances. This case analysis is maintained by casestatus.in based on publicly available court records.
-
19-Jun-2026
First hearing
Initial hearing scheduled
-
17-Jun-2026
Case filed
Registration No. WP/23431/2026
Case Summary: WP 23431/2026 Outcome: Interim relief granted with case adjourned for final hearing. The Madras High Court granted interim directions allowing M/s. Tamilselvan Traders and M/s. Aurea Solar Pvt Ltd. to energize their solar power plants and connect to the grid on an interim basis, subject to the final outcome of the writ petitions. The court directed respondents to provide grid connectivity forthwith and adjourned the matter to 22.06.2026 for final hearing alongside related cases. The petitioners had challenged circular memos dated 27.05.2026 and 30.05.2026 that blocked solar/wind connectivity approvals despite the petitioners meeting all statutory requirements and obtaining necessary clearances. This case analysis is maintained by casestatus.in based on publicly available court records.