M/s. Adithya Allied Solutions Pvt ltd., vs The Tamil Nadu Power Distribution — WP/23202/2026
Case under Others Section 1. Next hearing: 22nd June 2026.
CNR: HCMA011336772026
Filing Number
WP/97324/2026
Filing Date
16-Jun-2026
Registration No
WP/23202/2026
Registration Date
16-Jun-2026
Judge
Honourable Mr.Justice Mohammed Shaffiq
Coram
Honourable Mr.Justice Mohammed Shaffiq
Bench Type
Single Bench
Category
Electricity ( 56 )
Judicial Branch
WRITSECTION
Last updated 21-Jun-2026
Acts & Sections
Petitioner(s)
-
1.M/s. Adithya Allied Solutions Pvt ltd.,
Adv. R.S.Pandiyaraj, ,S.P.Parthasarathy,M.SARAVANA KUMAR,V.PURUSHOTHAMAN
Respondent(s)
-
1.The Tamil Nadu Power Distribution
-
2.THE TAMIL NADU GREEN ENERGY CORPORATION LTD., (TNGECL),
-
3.THE TAMIL NADU TRANSMISSION CORPORATION LTD (TANTRANSCO),
-
4.THE DIRECTOR / TECHNICAL
-
5.THE CHIEF ENGINEER/ NCES (FAC)
-
6.The Superintending Engineer
Case History
-
22-Jun-2026
Next hearingPending
-
22-Jun-2026
For Admission
Honourable Mr.Justice Mohammed Shaffiq
-
19-Jun-2026
Honourable Mr.Justice Mohammed ShaffiqView PDF
CASE SUMMARY: WP 23202/2026 The Madras High Court granted interim relief to three solar energy companies (Adithya Allied Solutions, Rithika Solar Energy, and Sandraks Green Energy) challenging a May 27, 2026 circular that suspended approvals for solar and wind power connectivity. The court directed the Perambalur Electricity Distribution Circle to immediately energize the petitioners' power plants by providing grid connectivity as an interim measure, subject to the final outcome of the petitions. The matter was adjourned to June 22, 2026. This case analysis is maintained by casestatus.in based on publicly available court records.
-
19-Jun-2026
First hearing
Initial hearing scheduled
-
16-Jun-2026
Case filed
Registration No. WP/23202/2026
CASE SUMMARY: WP 23202/2026 The Madras High Court granted interim relief to three solar energy companies (Adithya Allied Solutions, Rithika Solar Energy, and Sandraks Green Energy) challenging a May 27, 2026 circular that suspended approvals for solar and wind power connectivity. The court directed the Perambalur Electricity Distribution Circle to immediately energize the petitioners' power plants by providing grid connectivity as an interim measure, subject to the final outcome of the petitions. The matter was adjourned to June 22, 2026. This case analysis is maintained by casestatus.in based on publicly available court records.