M/s. Adithya Allied Solutions Pvt ltd., vs The Tamil Nadu Power Distribution — WP/23202/2026

Case under Others Section 1. Next hearing: 22nd June 2026.

Next hearing 22-Jun-2026

CNR: HCMA011336772026

Filing Number

WP/97324/2026

Filing Date

16-Jun-2026

Registration No

WP/23202/2026

Registration Date

16-Jun-2026

Judge

Honourable Mr.Justice Mohammed Shaffiq

Coram

Honourable Mr.Justice Mohammed Shaffiq

Bench Type

Single Bench

Category

Electricity ( 56 )

Judicial Branch

WRITSECTION

Last updated 21-Jun-2026

Acts & Sections

Others Section 1

Petitioner(s)

  1. 1.M/s. Adithya Allied Solutions Pvt ltd.,

    Adv. R.S.Pandiyaraj, ,S.P.Parthasarathy,M.SARAVANA KUMAR,V.PURUSHOTHAMAN

Respondent(s)

  1. 1.The Tamil Nadu Power Distribution

  2. 2.THE TAMIL NADU GREEN ENERGY CORPORATION LTD., (TNGECL),

  3. 3.THE TAMIL NADU TRANSMISSION CORPORATION LTD (TANTRANSCO),

  4. 4.THE DIRECTOR / TECHNICAL

  5. 5.THE CHIEF ENGINEER/ NCES (FAC)

  6. 6.The Superintending Engineer

Case History

  1. 22-Jun-2026

    Next hearingPending

  2. 22-Jun-2026

    For Admission

    Honourable Mr.Justice Mohammed Shaffiq

  3. 19-Jun-2026

    Honourable Mr.Justice Mohammed ShaffiqView PDF

    CASE SUMMARY: WP 23202/2026 The Madras High Court granted interim relief to three solar energy companies (Adithya Allied Solutions, Rithika Solar Energy, and Sandraks Green Energy) challenging a May 27, 2026 circular that suspended approvals for solar and wind power connectivity. The court directed the Perambalur Electricity Distribution Circle to immediately energize the petitioners' power plants by providing grid connectivity as an interim measure, subject to the final outcome of the petitions. The matter was adjourned to June 22, 2026. This case analysis is maintained by casestatus.in based on publicly available court records.

  4. 19-Jun-2026

    First hearing

    Initial hearing scheduled

  5. 16-Jun-2026

    Case filed

    Registration No. WP/23202/2026

casestatus.in Summary

CASE SUMMARY: WP 23202/2026 The Madras High Court granted interim relief to three solar energy companies (Adithya Allied Solutions, Rithika Solar Energy, and Sandraks Green Energy) challenging a May 27, 2026 circular that suspended approvals for solar and wind power connectivity. The court directed the Perambalur Electricity Distribution Circle to immediately energize the petitioners' power plants by providing grid connectivity as an interim measure, subject to the final outcome of the petitions. The matter was adjourned to June 22, 2026. This case analysis is maintained by casestatus.in based on publicly available court records.