THE EXECUTIVE ENGINEER, KNNL vs THE SPECIAL LAND ACQUISITION OFFICER — MFA/104565/2025

Case under Right to Fair Compensation and Transparency in Land Acquisition Rehabilitation and Resettlement Act Section 74. Next hearing: : -.

Next hearing —

CNR: KAHC020193682025

Filing Number

MFA/104305/2025

Filing Date

11-Sep-2025

Registration No

MFA/104565/2025

Registration Date

17-Oct-2025

Judge

B.m.shyam Prasad , Shivashankar Amarannavar

Coram

B.m.shyam Prasad , Shivashankar Amarannavar

Bench Type

Division Bench

Category

MFA ( 124 )

Sub-Category

LAC-RFCTLARR (Right to fair compensation and transparency in land acquisition , rehabilitation and resettlement act) ( 77 )

Judicial Branch

Judicial Section

Last updated 25-Apr-2026

Acts & Sections

Right to Fair Compensation and Transparency in Land Acquisition Rehabilitation and Resettlement Act Section 74

Petitioner(s)

  1. 1.THE EXECUTIVE ENGINEER, KNNL

    Adv. IRANAGOUDA K KABBUR

Respondent(s)

  1. 1.THE SPECIAL LAND ACQUISITION OFFICER

  2. 2.VISHWANATH S/O VIRUPAX HULLOLLI

Case History

  1. Next hearingPending

  2. 26-Mar-2026

    B.m.shyam Prasad,shivashankar AmarannavarView PDF

    Summary: The High Court of Karnataka granted an interim stay on the impugned judgment and award in a land acquisition compensation case for the Karimasuti Lift Irrigation Project, subject to the appellant depositing 50% of the award amount with the reference court within 8 weeks to be invested in a fixed deposit with a nationalized bank. The claimant (respondent No.2) is permitted to file an application for withdrawal, and the case is adjourned with notice returnable by 23.06.2026. This case analysis is maintained by casestatus.in based on publicly available court records.

  3. 26-Mar-2026

    Hearing - Interlocutory Appln

    B.m.shyam Prasad , Shivashankar Amarannavar

  4. 11-Sep-2025

    Case filed

    Registration No. MFA/104565/2025

casestatus.in Summary

Summary: The High Court of Karnataka granted an interim stay on the impugned judgment and award in a land acquisition compensation case for the Karimasuti Lift Irrigation Project, subject to the appellant depositing 50% of the award amount with the reference court within 8 weeks to be invested in a fixed deposit with a nationalized bank. The claimant (respondent No.2) is permitted to file an application for withdrawal, and the case is adjourned with notice returnable by 23.06.2026. This case analysis is maintained by casestatus.in based on publicly available court records.