THE EXECUTIVE ENGINEER vs THE DEPUTY COMMISSIONER — MFA/101425/2025

Case under Right to Fair Compensation and Transparency in Land Acquisition Rehabilitation and Resettlement Act Section 74. Next hearing: : -.

Next hearing —

CNR: KAHC020058652025

Filing Number

MFA/101235/2025

Filing Date

11-Mar-2025

Registration No

MFA/101425/2025

Registration Date

07-Apr-2025

Judge

B.m.shyam Prasad , Shivashankar Amarannavar

Coram

B.m.shyam Prasad , Shivashankar Amarannavar

Bench Type

Division Bench

Category

MFA ( 124 )

Sub-Category

LAC-RFCTLARR (Right to fair compensation and transparency in land acquisition , rehabilitation and resettlement act) ( 77 )

Judicial Branch

Judicial Section

Last updated 25-Apr-2026

Acts & Sections

Right to Fair Compensation and Transparency in Land Acquisition Rehabilitation and Resettlement Act Section 74

Petitioner(s)

  1. 1.THE EXECUTIVE ENGINEER

    Adv. S M KALWAD

Respondent(s)

  1. 1.THE DEPUTY COMMISSIONER

  2. 2.THE SPECIAL LAND ACQUISITION OFFICER

  3. 3.SRI LAXMAN TEERTHAPPA BADIGER

  4. 4.SRI KALAPPA S/O TEERTHAPPA BADIGER

  5. 5.SRI RAMACHANDRA S/O TEERTHAPPA BADIGER

Case History

  1. Next hearingPending

  2. 26-Mar-2026

    B.m.shyam Prasad,shivashankar AmarannavarView PDF

    Summary: The High Court of Karnataka at Dharwad granted an interim stay of the impugned judgment and award in a land acquisition compensation case for the Hulikatti Branch Canal Project, subject to the appellant depositing 50% of the award amount with the reference court within 8 weeks, to be invested in a fixed deposit with a nationalized bank with auto-renewal instructions. The case is scheduled for next hearing on 23.06.2026, with claimants permitted to file applications for withdrawal of the deposited amount. This case analysis is maintained by casestatus.in based on publicly available court records.

  3. 19-Jun-2025

    Non-Compliance Of Office-Objns For 1St Time

    Addl. Registrar Judicial

  4. 11-Mar-2025

    Case filed

    Registration No. MFA/101425/2025

casestatus.in Summary

Summary: The High Court of Karnataka at Dharwad granted an interim stay of the impugned judgment and award in a land acquisition compensation case for the Hulikatti Branch Canal Project, subject to the appellant depositing 50% of the award amount with the reference court within 8 weeks, to be invested in a fixed deposit with a nationalized bank with auto-renewal instructions. The case is scheduled for next hearing on 23.06.2026, with claimants permitted to file applications for withdrawal of the deposited amount. This case analysis is maintained by casestatus.in based on publicly available court records.