M/S SIEMENS GAMESA RENEWABLE ENERGY PROJECTS PRIVATE LIMITED vs ADDITIONAL DIRECTOR, Advocate - MADHU N RAO — WP/25804/2024

Case under Constitution of India Section 226,227. Next hearing: 21st July 2026.

Next hearing 21-Jul-2026

CNR: KAHC010537002024

Filing Number

WP/25204/2024

Filing Date

12-Sep-2024

Registration No

WP/25804/2024

Registration Date

19-Sep-2024

Judge

B M Shyam Prasad

Coram

B M Shyam Prasad

Bench Type

Single Bench

Category

WP ( 144 )

Sub-Category

RES-Residuary ( 112 )

Judicial Branch

Judicial Section

Last updated 11-Jun-2026

Acts & Sections

Constitution of India Section 226,227

Petitioner(s)

  1. 1.M/S SIEMENS GAMESA RENEWABLE ENERGY PROJECTS PRIVATE LIMITED

    Adv. G L MOHAN MAIYA

Respondent(s)

  1. 1.ADDITIONAL DIRECTOR, Advocate - MADHU N RAO

  2. 2.ADDITIONAL COMMISSIONER

    Adv. MADHU N RAO

Case History

  1. 21-Jul-2026

    Next hearingPending

  2. 21-Jul-2026

    Hearing - Interlocutory Appln

    B M Shyam Prasad

  3. 09-Jun-2026

    B M Shyam PrasadView PDF

    Case Summary: In WP 25804/2024, the High Court of Karnataka adjourned the petition filed by Siemens Gamesa Renewable Energy Projects Private Limited against the Additional Director and Additional Commissioner as requested by respondents' counsel. The case is scheduled for the next hearing on 21.07.2026, and the interim order previously granted has been extended and will remain in force until the next hearing date. This case analysis is maintained by casestatus.in based on publicly available court records.

  4. 18-Mar-2026

    Hearing - Interlocutory Appln

    S Sunil Dutt Yadav

  5. 25-Sep-2024

    First hearing

    Initial hearing scheduled

  6. 12-Sep-2024

    Case filed

    Registration No. WP/25804/2024

casestatus.in Summary

Case Summary: In WP 25804/2024, the High Court of Karnataka adjourned the petition filed by Siemens Gamesa Renewable Energy Projects Private Limited against the Additional Director and Additional Commissioner as requested by respondents' counsel. The case is scheduled for the next hearing on 21.07.2026, and the interim order previously granted has been extended and will remain in force until the next hearing date. This case analysis is maintained by casestatus.in based on publicly available court records.