BEAS VALLEY POWER CORPORATION LIMITED(Not Applicable) vs M/S ABIR INFRASTRUCTURE PRIVATE LIMITED(Not Applicable) — ARB.C/180/2025
Case under Arbitration and Conciliation Act, 1996 Section 14(2),15(2). Status: Orders. Next hearing: 30th October 2026.
CNR: HPHC010397592024
Filing Number
ARB.C/32105/2024
Filing Date
27-Aug-2024
Registration No
ARB.C/180/2025
Registration Date
18-Jun-2025
Judge
Hon'ble The Chief Justice Gurmeet Singh Sandhawalia
Coram
Hon'ble The Chief Justice Gurmeet Singh Sandhawalia
Bench Type
Single
Judicial Branch
Civil Section
Last updated 30-Sep-2026
Acts & Sections
Petitioner(s)
-
1.BEAS VALLEY POWER CORPORATION LIMITED(Not Applicable)
Adv. Vandana Misra
Respondent(s)
-
1.M/S ABIR INFRASTRUCTURE PRIVATE LIMITED(Not Applicable)
Adv. ,NEMO 1123
Case History
-
30-Oct-2026
Next hearingPending
-
30-Oct-2026
Orders
Hon'ble The Chief Justice Gurmeet Singh Sandhawalia
-
18-Sep-2026
Hon'ble The Chief Justice Gurmeet Singh SandhawaliaView PDF
-
18-Sep-2026
Orders
Hon'ble The Chief Justice Gurmeet Singh Sandhawalia
-
24-Jul-2026
Hon'ble The Chief Justice Gurmeet Singh SandhawaliaView PDF
-
05-Dec-2025
Orders
Hon'ble The Chief Justice Gurmeet Singh Sandhawalia
-
17-Oct-2025
Hon'ble The Chief Justice Gurmeet Singh SandhawaliaView PDF
-
17-Oct-2025
Orders
Hon'ble The Chief Justice Gurmeet Singh Sandhawalia
-
05-Sep-2025
Hon'ble The Chief Justice Gurmeet Singh SandhawaliaView PDF
-
05-Sep-2025
Orders
Hon'ble The Chief Justice Gurmeet Singh Sandhawalia
-
01-Aug-2025
Hon'ble The Chief Justice Gurmeet Singh SandhawaliaView PDF
-
01-Aug-2025
Orders
Hon'ble The Chief Justice Gurmeet Singh Sandhawalia
-
20-Jun-2025
Hon'ble The Chief Justice Gurmeet Singh SandhawaliaView PDF
-
20-Jun-2025
First hearing
Initial hearing scheduled
-
27-Aug-2024
Case filed
Registration No. ARB.C/180/2025