M/s Kaleshwari Power Products Pvt. Ltd. through its AR Amit Tomar vs Northern Central Railway,through its Sr. Divisional Material Manager — 23/2025
Case under Arbitration and Conciliation Act Section 34. Status: Objection/Disposal. Next hearing: 23rd March 2026 Date Not Updated.
Arbitration Cases
CNR: UPAG190002172025
Filing Number
222/2025
Filing Date
28-Oct-2025
Registration No
23/2025
Registration Date
28-Oct-2025
Court
Commercial Court Agra
Judge
1-Commercial Court No. 01
Last updated 07-May-2026
Acts & Sections
Petitioner(s)
-
1.M/s Kaleshwari Power Products Pvt. Ltd. through its AR Amit Tomar
Adv. Naresh Kumar Sharma
Respondent(s)
-
1.Northern Central Railway,through its Sr. Divisional Material Manager
-
2.Sr. Section Engineer (Power), Agra Fort
-
3.Sr. Section Engineer (C And W,ACG), Agra Cantt
-
4.Sr. Section Engineer (Power), NCR Mathura
-
5.Zonal Micro And Small Enterprises Facilitation Council
Case History
-
23-Mar-2026
Next hearingPending
-
10-Mar-2026
Objection/Disposal
Commercial Court No. 01
-
20-Feb-2026
Objection/Disposal
Commercial Court No. 01
-
11-Feb-2026
Objection/Disposal
Commercial Court No. 01
-
17-Jan-2026
Steps
Commercial Court No. 01
-
03-Jan-2026
Steps
Commercial Court No. 01
-
09-Dec-2025
Steps
Commercial Court No. 01
-
13-Nov-2025
First hearing
Initial hearing scheduled
-
28-Oct-2025
Case filed
Registration No. 23/2025