U.O.I through General Manager,NCR,Prayagraj by Senior Divisional Engineer-I,NCR Agra vs M/s Raj Construction Company — 33/2025

Case under Arbitration and Conciliation Act Section 34(3). Disposed: Contested--ALLOWED on 08th July 2026.

Case disposed

Misc. Civil Cases

CNR: UPAG190002012025

Filing Number

206/2025

Filing Date

24-Sep-2025

Registration No

33/2025

Registration Date

24-Sep-2025

Court

Commercial Court Agra

Judge

2-Commercial Court No. 02

Decision Date

08-Jul-2026

Nature of Disposal

Contested--ALLOWED

Last updated 06-Sep-2026

Acts & Sections

Arbitration and Conciliation Act Section 34(3)

Petitioner(s)

  1. 1.U.O.I through General Manager,NCR,Prayagraj by Senior Divisional Engineer-I,NCR Agra

    Adv. Mragesh Kulshrestha

Respondent(s)

  1. 1.M/s Raj Construction Company

Case History

  1. Case disposedDisposed

  2. 08-Jul-2026

    Disposed

    Commercial Court No. 02

  3. 02-Jul-2026

    Order/Disposal

    Commercial Court No. 02

  4. 01-Jun-2026

    Order/Disposal

    Commercial Court No. 02

  5. 13-May-2026

    Order/Disposal

    Commercial Court No. 02

  6. 29-Apr-2026

    Order/Disposal

    Commercial Court No. 02

  7. 09-Apr-2026

    Arguments

    Commercial Court No. 02

  8. 24-Mar-2026

    Arguments

    Commercial Court No. 02

  9. 18-Mar-2026

    Arguments

    Commercial Court No. 02

  10. 24-Feb-2026

    For Disposal

    Commercial Court No. 02

  11. 11-Feb-2026

    For Disposal

    Commercial Court No. 02

  12. 22-Jan-2026

    For Disposal

    Commercial Court No. 02

  13. 07-Jan-2026

    Objection/Disposal

    Commercial Court No. 02

  14. 12-Dec-2025

    Steps

    Commercial Court No. 02

  15. 28-Nov-2025

    Steps

    Commercial Court No. 02

  16. 11-Nov-2025

    Steps

    Commercial Court No. 02

  17. 27-Oct-2025

    First hearing

    Initial hearing scheduled

  18. 24-Sep-2025

    Case filed

    Registration No. 33/2025