Vish Wind Infrastructure LLP., Represented by Mr.S.Balasubramanian Assistant General Manager vs Jebasam Alexander Advocate - Thiru.S.D.Shunmuga Jegan — 95/2023

Case under Code of Civil Procedure Section 25d,27c,27c. Status: Trial. Next hearing: 19th June 2026.

Trial Next hearing 19-Jun-2026 this date has passed

OS - Original Suit

CNR: TNTL060001212023

Filing Number

146/2023

Filing Date

28-Feb-2023

Registration No

95/2023

Registration Date

09-Mar-2023

Court

Principal District Munsif Court, Tirunelveli

Judge

13-I Additional District Munsif

Last updated 10-Jun-2026

Acts & Sections

Code of Civil Procedure Section 25d,27c,27c

Petitioner(s)

  1. 1.Vish Wind Infrastructure LLP., Represented by Mr.S.Balasubramanian Assistant General Manager

    Adv. M.P.Damodaran

Respondent(s)

  1. 1.Jebasam Alexander Advocate - Thiru.S.D.Shunmuga Jegan

  2. 2.Sutheesh kumar

    Adv. Thiru.V.Vinoth

Case History

  1. 19-Jun-2026

    Next hearingPending

  2. 22-Apr-2026

    Trial

    I Additional District Munsif

  3. 14-Mar-2026

    Lok Adalat

    I Additional District Munsif

  4. 27-Feb-2026

    Lok Adalat

    I Additional District Munsif

  5. 13-Dec-2025

    Trial

    I Additional District Munsif

  6. 03-Dec-2025

    Lok Adalat

    I Additional District Munsif

  7. 14-Nov-2025

    IAView PDF

    The 1st Additional District Civil Court in Tirunelveli allowed the petition filed by Vish Wind Infrastructure LLP. The court vacated the dismissal order of the original case and permitted it to be restored, granting the petitioner an opportunity to prosecute the suit against the respondents for permanent injunction relief. The court found the petitioner ready to proceed despite previous adjournments caused by lawyer absence and health issues. This case analysis is maintained by casestatus.in based on publicly available court records.

  8. 14-Nov-2025

    Restored

    I Additional District Munsif

  9. 14-Nov-2025

    Trial

    I Additional District Munsif

  10. 14-Nov-2025

    Trial

    I Additional District Munsif

  11. 24-Mar-2025

    Disposed

    I Additional District Munsif

  12. 06-Mar-2025

    Trial

    I Additional District Munsif

  13. 26-Feb-2025

    Trial

    I Additional District Munsif

  14. 06-Feb-2025

    Trial

    I Additional District Munsif

  15. 06-Jan-2025

    Trial

    I Additional District Munsif

  16. 11-Dec-2024

    Trial

    I Additional District Munsif

  17. 05-Dec-2024

    Trial

    I Additional District Munsif

  18. 21-Nov-2024

    Trial

    I Additional District Munsif

  19. 30-Oct-2024

    Trial

    I Additional District Munsif

  20. 30-Sep-2024

    Trial

    I Additional District Munsif

  21. 14-Sep-2024

    Lok Adalat

    I Additional District Munsif

  22. 30-Aug-2024

    Lok Adalat

    I Additional District Munsif

  23. 01-Aug-2024

    IA / Ea Pending / Cmp Pending / CRP Pending / Cma Pending

    I Additional District Munsif

  24. 11-Jul-2024

    IA / Ea Pending / Cmp Pending / CRP Pending / Cma Pending

    I Additional District Munsif

  25. 18-Jun-2024

    IA / Ea Pending / Cmp Pending / CRP Pending / Cma Pending

    I Additional District Munsif

  26. 18-Apr-2024

    IA / Ea Pending / Cmp Pending / CRP Pending / Cma Pending

    I Additional District Munsif

  27. 27-Feb-2024

    IA / Ea Pending / Cmp Pending / CRP Pending / Cma Pending

    I Additional District Munsif

  28. 29-Jan-2024

    IA / Ea Pending / Cmp Pending / CRP Pending / Cma Pending

    I Additional District Munsif

  29. 21-Dec-2023

    Written Statement

    I Additional District Munsif

  30. 01-Dec-2023

    Written Statement

    I Additional District Munsif

  31. 18-Oct-2023

    Written Statement

    I Additional District Munsif

  32. 12-Sep-2023

    Written Statement

    I Additional District Munsif

  33. 10-Aug-2023

    Written Statement

    I Additional District Munsif

  34. 13-Jul-2023

    Written Statement

    I Additional District Munsif

  35. 16-Jun-2023

    Written Statement

    I Additional District Munsif

  36. 11-Apr-2023

    Written Statement

    I Additional District Munsif

  37. 09-Mar-2023

    First hearing

    Initial hearing scheduled

  38. 28-Feb-2023

    Case filed

    Registration No. 95/2023

casestatus.in Summary

The 1st Additional District Civil Court in Tirunelveli allowed the petition filed by Vish Wind Infrastructure LLP. The court vacated the dismissal order of the original case and permitted it to be restored, granting the petitioner an opportunity to prosecute the suit against the respondents for permanent injunction relief. The court found the petitioner ready to proceed despite previous adjournments caused by lawyer absence and health issues. This case analysis is maintained by casestatus.in based on publicly available court records.

Explore other courts