Thiru J.Selva Jeya Jegan and 10 Ors vs Daison Moses Muthuraj and 1 Ors — 4000272/2016

Case under --- Section 26. Disposed: Contested--DECREED on 18th April 2026.

OS - Original Suit

CNR: TNKK050000152026

Case disposed

Filing Number

12/2026

Filing Date

20-10-2016

Registration No

4000272/2016

Registration Date

03-11-2016

Court

Special Sub Court to deal with forest offence cases, Nagercoil, Kanyakumari

Judge

1-Special Judge for Forest Offence Cases

Decision Date

18th April 2026

Nature of Disposal

Contested--DECREED

Acts & Sections

--- Section 26

Petitioner(s)

Thiru J.Selva Jeya Jegan and 10 Ors

Adv. M.Antony Raja Kumar

J.Miga Anbu Jeyakumar

Yeasudhass

Tmt.Paramayee @ Jennet

Tmt.Jeyarani

Tmt.Papa

Tmt.Lilly

Tmt.Regila

Tmt.Regi

Tmt.Selvam

Tmt.Mary Iyda Christy Inidha

Respondent(s)

Daison Moses Muthuraj and 1 Ors

Anbiah

Hearing History

Judge: 1-Special Judge for Forest Offence Cases

18-04-2026

Disposed

02-04-2026

ARGUMENTS

30-03-2026

ARGUMENTS

17-03-2026

ARGUMENTS

11-03-2026

ARGUMENTS

Final Orders / Judgements

18-04-2026
Copy of Judgment

Court Summary The Special Court for Forest Offence Cases in Nagercoil decreed a suit in favor of 11 plaintiffs against two defendants regarding disputed property pathways. The court found that the 1st defendant unlawfully encroached on a 5-foot pathway (B Schedule property) in survey number 817/5B2 by constructing a compound wall, and ordered him to remove the construction within 4 weeks. The court granted declarations confirming plaintiffs' ownership of the pathways and imposed permanent injunctions preventing the defendants from further disturbance, while each party bore their own costs. This case analysis is maintained by casestatus.in based on publicly available court records.

Interim Orders

30-01-2026
Deposition
06-02-2026
Deposition
casestatus.in Summary

Court Summary The Special Court for Forest Offence Cases in Nagercoil decreed a suit in favor of 11 plaintiffs against two defendants regarding disputed property pathways. The court found that the 1st defendant unlawfully encroached on a 5-foot pathway (B Schedule property) in survey number 817/5B2 by constructing a compound wall, and ordered him to remove the construction within 4 weeks. The court granted declarations confirming plaintiffs' ownership of the pathways and imposed permanent injunctions preventing the defendants from further disturbance, while each party bore their own costs. This case analysis is maintained by casestatus.in based on publicly available court records.

Browse Related Cases

More from this court

Special Sub Court to deal with forest offence cases, Nagercoil, Kanyakumari All courts →

Explore other courts

Search Another Case