M/s Horizon Metal Tech Private Limited, rep by its Auth.,Signatory Mr.Ashok Sharma vs M/s Sri Murugan Foundry Equipment, rep by its Managing partner R.Murugaiyan Advocate - Senthilnathan.R — 7/2025
Case under Code of Civil Procedure Section Order VII rule 1. Disposed: Contested--Partially Allowed on 18th March 2026.
COS - Commercial Original Suit
CNR: TNCB220000132025
e-Filing Number
04-02-2025
Filing Number
15/2025
Filing Date
05-02-2025
Registration No
7/2025
Registration Date
05-02-2025
Court
Commercial Court in the Cadre of District Judge, Coimbatore
Judge
1-COMMERCIAL COURT IN THE CADRE OF DISTRICT JUDGE
Decision Date
18th March 2026
Nature of Disposal
Contested--Partially Allowed
Acts & Sections
Petitioner(s)
M/s Horizon Metal Tech Private Limited, rep by its Auth.,Signatory Mr.Ashok Sharma
Adv. POORVAJA A R
Respondent(s)
M/s Sri Murugan Foundry Equipment, rep by its Managing partner R.Murugaiyan Advocate - Senthilnathan.R
R Murugaiyan
Adv. R.Senthilnathan
R Manonmani
Adv. R.Senthilnathan
Deepa Murugaiyan
Adv. R.Senthilnathan
Hearing History
Judge: 1-COMMERCIAL COURT IN THE CADRE OF DISTRICT JUDGE
Disposed
Judgement
Judgement
Judgement
For further Proceedings
| Date | Purpose |
|---|---|
| 18-03-2026 | Disposed |
| 17-03-2026 | Judgement |
| 16-03-2026 | Judgement |
| 12-03-2026 | Judgement |
| 11-03-2026 | For further Proceedings |
Final Orders / Judgements
The Coimbatore Commercial Court partly decreed the suit filed by Horizon Metal Tech Pvt. Ltd. against Sri Murugan Foundry Equipment and its partners. The court awarded Rs. 40,79,026 for spare parts and one-third of the loss of profits claim (Rs. 33,26,103), both with 18% interest from the suit date, plus Rs. 2,99,500 as cost of suit, rejecting portions of the plaintiff's claim for additional spare parts and full loss of profits. This case analysis is maintained by casestatus.in based on publicly available court records.
Interim Orders
The Coimbatore Commercial Court partly decreed the suit filed by Horizon Metal Tech Pvt. Ltd. against Sri Murugan Foundry Equipment and its partners. The court awarded Rs. 40,79,026 for spare parts and one-third of the loss of profits claim (Rs. 33,26,103), both with 18% interest from the suit date, plus Rs. 2,99,500 as cost of suit, rejecting portions of the plaintiff's claim for additional spare parts and full loss of profits. This case analysis is maintained by casestatus.in based on publicly available court records.