Project Director National Highway Authority of India Unit Amravati vs Subhash Sampat Kalbande — 129/2025

Case under Limitation Act Section 5. Disposed: Uncontested--ALLOWED / GRANTED AFTER FULL HEARING on 16th March 2026.

Case disposed

Civil M.A. - Civil Misc. Application

CNR: MHWS010012042025

e-Filing Number

15-11-2025

Filing Number

535/2025

Filing Date

03-Dec-2025

Registration No

129/2025

Registration Date

22-Dec-2025

Court

District and Sessions Court, Washim

Judge

1-Principal District and Sessions Judge, Washim

Decision Date

16-Mar-2026

Nature of Disposal

Uncontested--ALLOWED / GRANTED AFTER FULL HEARING

Last updated 15-Jun-2026

Acts & Sections

Limitation Act Section 5

Petitioner(s)

  1. 1.Project Director National Highway Authority of India Unit Amravati

    Adv. TAYADE VINOD BHIMRAO

Respondent(s)

  1. 1.Subhash Sampat Kalbande

  2. 2.Additional Collector and Arbitratior Washim

  3. 3.Sub-Divisional Officer and Land Acquisition Officer Washim

Case History

  1. Case disposedDisposed

  2. 16-Mar-2026

    Order on ExhibitView PDF

    The Principal District Judge, Washim, granted NHAI's application for condonation of a seven-day delay in filing an application under Section 34 of the Arbitration Act, finding just and sufficient grounds for the delay. The court directed the office to register the application as per rules and disposed of the matter accordingly. This case analysis is maintained by casestatus.in based on publicly available court records.

  3. 16-Mar-2026

    Disposed

    Principal District and Sessions Judge, Washim

  4. 20-Feb-2026

    Ex-Parte Order

    Principal District and Sessions Judge, Washim

  5. 10-Feb-2026

    Appearance

    Principal District and Sessions Judge, Washim

  6. 21-Jan-2026

    Awaiting Notice

    Principal District and Sessions Judge, Washim

  7. 23-Dec-2025

    First hearing

    Initial hearing scheduled

  8. 03-Dec-2025

    Case filed

    Registration No. 129/2025

casestatus.in Summary

The Principal District Judge, Washim, granted NHAI's application for condonation of a seven-day delay in filing an application under Section 34 of the Arbitration Act, finding just and sufficient grounds for the delay. The court directed the office to register the application as per rules and disposed of the matter accordingly. This case analysis is maintained by casestatus.in based on publicly available court records.