Raosaheb Prabhu Jagtap vs Dharma Dhondiba Jagtap — 186/2021

Case under Specific Relief Act Section 38. Status: Awaiting Report of Commissioner. Next hearing: 09th June 2026.

R.C.S. - Regular Civil Suit

CNR: MHSO190010202021

Awaiting Report of Commissioner

Next Hearing

09th June 2026

Filing Number

244/2021

Filing Date

13-05-2021

Registration No

186/2021

Registration Date

17-05-2021

Court

Civil Court Junior Division , Mohal

Judge

3-II Jt. Civil Judge J. D. JMFC Mohol

Acts & Sections

Specific Relief Act Section 38

Petitioner(s)

Raosaheb Prabhu Jagtap

Adv. Shaikh Muinuddin Gafoorsaheb

Respondent(s)

Dharma Dhondiba Jagtap

Adnyansidha Dhondiba Jagtap

Hearing History

Judge: 3-II Jt. Civil Judge J. D. JMFC Mohol

13-03-2026

Awaiting Report of Commissioner

21-01-2026

Awaiting Report of Commissioner

20-12-2025

Awaiting Report of Commissioner

28-10-2025

Compliance

25-09-2025

Compliance

Interim Orders

18-09-2021
Order on Exhibit

Case Summary: RCS No. 186/2021 Plaintiff Raosaheb Prabhu Jagtap's application to appoint a Deputy Survey and Land Records Officer as court-commissioner was allowed on 18 September 2021. The court appointed the Dy.S.L.R., Mohol to conduct on-site measurement and investigation of disputed land blocks (261, 262, 260/1/A, and 260/1/B) at village Wadwal to document alleged encroachments and fix boundary marks, with a report due by 30 October 2021. Both parties were directed to deposit respective government fees for the measurement work. This case analysis is maintained by casestatus.in based on publicly available court records.

casestatus.in Summary

Case Summary: RCS No. 186/2021 Plaintiff Raosaheb Prabhu Jagtap's application to appoint a Deputy Survey and Land Records Officer as court-commissioner was allowed on 18 September 2021. The court appointed the Dy.S.L.R., Mohol to conduct on-site measurement and investigation of disputed land blocks (261, 262, 260/1/A, and 260/1/B) at village Wadwal to document alleged encroachments and fix boundary marks, with a report due by 30 October 2021. Both parties were directed to deposit respective government fees for the measurement work. This case analysis is maintained by casestatus.in based on publicly available court records.

Browse Related Cases

Cases under same legislation

More from this court

Civil Court Junior Division , Mohal All courts →

Explore other courts