Baban Sitaram Bhalekar and ors vs M/s. S.D.O. Land Acquisition Mahad Division and ors — 97/2020

Case under Land Acquisition Act Section 28-A(3). Disposed: Contested--PARTLY ALLOWED on 02nd May 2026.

L.A.R. - Land Ref.

CNR: MHRG190007872023

Case disposed

Filing Number

97/2020

Filing Date

10-12-2020

Registration No

97/2020

Registration Date

10-12-2020

Court

Court of Civil Judge S.D. Mahad

Judge

1-Civil Judge Senior Division, Mahad

Decision Date

02nd May 2026

Nature of Disposal

Contested--PARTLY ALLOWED

Acts & Sections

Land Acquisition Act Section 28-A(3)

Petitioner(s)

Baban Sitaram Bhalekar and ors

Adv. Navale B. T.

Respondent(s)

M/s. S.D.O. Land Acquisition Mahad Division and ors

Hearing History

Judge: 1-Civil Judge Senior Division, Mahad

02-05-2026

Disposed

08-04-2026

Arguments

02-04-2026

Arguments

23-03-2026

Evidence

12-03-2026

Evidence

Final Orders / Judgements

02-05-2026
Copy of Judgment

Summary: Case 97/2020 - Baban Sitaram Bhalekar vs. S.D.O. Land Acquisition The court partly allowed the reference for enhanced compensation for 1,850 sq. meters of agricultural land in Bhomjai village acquired for the Nageshwari Dam project. The judge found the original compensation inadequate, determining the market value at the time of notification (1999) was Rs. 700/- per sq. meter rather than the rate originally awarded, and granted enhanced compensation at that rate plus statutory benefits including 30% solatium and 12% additional component with interest. This case analysis is maintained by casestatus.in based on publicly available court records.

Interim Orders

casestatus.in Summary

Summary: Case 97/2020 - Baban Sitaram Bhalekar vs. S.D.O. Land Acquisition The court partly allowed the reference for enhanced compensation for 1,850 sq. meters of agricultural land in Bhomjai village acquired for the Nageshwari Dam project. The judge found the original compensation inadequate, determining the market value at the time of notification (1999) was Rs. 700/- per sq. meter rather than the rate originally awarded, and granted enhanced compensation at that rate plus statutory benefits including 30% solatium and 12% additional component with interest. This case analysis is maintained by casestatus.in based on publicly available court records.