Krishna Mahadeo Dasgaonkar vs M/s. S.D.O. Land Acquisition Mahad Division and ors — 96/2020
Case under Land Acquisition Act Section 28-A(3). Disposed: Contested--PARTLY ALLOWED on 02nd May 2026.
L.A.R. - Land Ref.
CNR: MHRG190007832023
Filing Number
96/2020
Filing Date
10-Dec-2020
Registration No
96/2020
Registration Date
10-Dec-2020
Court
Court of Civil Judge S.D. Mahad
Judge
1-Civil Judge Senior Division, Mahad
Decision Date
02-May-2026
Nature of Disposal
Contested--PARTLY ALLOWED
Last updated 29-May-2026
Acts & Sections
Petitioner(s)
-
1.Krishna Mahadeo Dasgaonkar
Adv. Navale B. T.
Respondent(s)
-
1.M/s. S.D.O. Land Acquisition Mahad Division and ors
Case History
-
Case disposedDisposed
-
02-May-2026
Order on ExhibitView PDF
-
02-May-2026
Copy of JudgmentView PDF
Case Summary: Krishna Mahadeo Dasgaonkar vs. S.D.O. Land Acquisition (96/2020) The court partially allowed the applicant's reference for enhanced land compensation under the Land Acquisition Act, 1894. The applicant's land (6,370 sq. meters in Bhomjai village) was acquired for the Nageshwari Dam project. The court found that the Special Land Acquisition Officer's original award of Rs. 97,500-68,500 per hectare was inadequate, as it failed to consider relevant factors like proximity to highways, railway stations, industrial areas (M.I.D.C. Mahad), and non-agricultural potential. The court awarded enhanced compensation at Rs. 700 per square meter (after deducting 65% development costs from comparable sales), plus 30% solatium, 12% additional component, and interest at 9-15% per annum. This case analysis is maintained by casestatus.in based on publicly available court records.
-
02-May-2026
Disposed
Civil Judge Senior Division, Mahad
-
08-Apr-2026
Arguments
Civil Judge Senior Division, Mahad
-
02-Apr-2026
Arguments
Civil Judge Senior Division, Mahad
-
23-Mar-2026
Evidence
Civil Judge Senior Division, Mahad
-
12-Mar-2026
Evidence
Civil Judge Senior Division, Mahad
-
26-Feb-2026
Evidence
Civil Judge Senior Division, Mahad
-
29-Jan-2026
Evidence
Civil Judge Senior Division, Mahad
-
15-Jan-2026
Evidence
Civil Judge Senior Division, Mahad
-
01-Jan-2026
Order on ExhibitView PDF
-
01-Jan-2026
Evidence
Civil Judge Senior Division, Mahad
-
11-Dec-2025
Evidence
Civil Judge Senior Division, Mahad
-
13-Nov-2025
Evidence
Civil Judge Senior Division, Mahad
-
06-Nov-2025
Evidence
Civil Judge Senior Division, Mahad
-
16-Oct-2025
Order on ExhibitView PDF
-
16-Oct-2025
Evidence Part Heard
Civil Judge Senior Division, Mahad
-
23-Sep-2025
Evidence Part Heard
Civil Judge Senior Division, Mahad
-
18-Sep-2025
Evidence
Civil Judge Senior Division, Mahad
-
14-Aug-2025
Evidence
Civil Judge Senior Division, Mahad
-
24-Jul-2025
Evidence
Civil Judge Senior Division, Mahad
-
10-Jul-2025
Evidence Part Heard
Civil Judge Senior Division, Mahad
-
19-Jun-2025
Hearing
Civil Judge Senior Division, Mahad
-
24-Apr-2025
Order on ExhibitView PDF
-
24-Apr-2025
Amended Plaint
Civil Judge Senior Division, Mahad
-
27-Mar-2025
Argument on Exh.____Ready
Civil Judge Senior Division, Mahad
-
06-Mar-2025
Argument on Exh.____Ready
Civil Judge Senior Division, Mahad
-
09-Jan-2025
Filing of Say on Exh___Ready
Civil Judge Senior Division, Mahad
-
07-Nov-2024
Filing of Say on Exh___Ready
Civil Judge Senior Division, Mahad
-
08-Aug-2024
Filing of Say on Exh___Ready
Civil Judge Senior Division, Mahad
-
02-May-2024
Hearing
Civil Judge Senior Division, Mahad
-
28-Mar-2024
Hearing
Civil Judge Senior Division, Mahad
-
21-Dec-2023
Hearing
Civil Judge Senior Division, Mahad
-
12-Oct-2023
First hearing
Initial hearing scheduled
-
10-Dec-2020
Case filed
Registration No. 96/2020
Case Summary: Krishna Mahadeo Dasgaonkar vs. S.D.O. Land Acquisition (96/2020) The court partially allowed the applicant's reference for enhanced land compensation under the Land Acquisition Act, 1894. The applicant's land (6,370 sq. meters in Bhomjai village) was acquired for the Nageshwari Dam project. The court found that the Special Land Acquisition Officer's original award of Rs. 97,500-68,500 per hectare was inadequate, as it failed to consider relevant factors like proximity to highways, railway stations, industrial areas (M.I.D.C. Mahad), and non-agricultural potential. The court awarded enhanced compensation at Rs. 700 per square meter (after deducting 65% development costs from comparable sales), plus 30% solatium, 12% additional component, and interest at 9-15% per annum. This case analysis is maintained by casestatus.in based on publicly available court records.