Jamila Hamid Mahalkar and 1 vs May Deputy Collector (Land Acquisition Officer) Sub Division Officer, Mahad — 84/2020
Case under Land Acquisition Act Section 18. Disposed: Contested--PARTLY ALLOWED on 02nd May 2026.
L.A.R. - Land Ref.
CNR: MHRG190007472023
Filing Number
84/2020
Filing Date
17-Sep-2020
Registration No
84/2020
Registration Date
04-Dec-2020
Court
Court of Civil Judge S.D. Mahad
Judge
1-Civil Judge Senior Division, Mahad
Decision Date
02-May-2026
Nature of Disposal
Contested--PARTLY ALLOWED
Last updated 29-May-2026
Acts & Sections
Petitioner(s)
-
1.Jamila Hamid Mahalkar and 1
Adv. Navale B. T.
Respondent(s)
-
1.May Deputy Collector (Land Acquisition Officer) Sub Division Officer, Mahad
-
2.May. Collector, Raigad
-
3.May. Executive Engineering, Hetwane
Case History
-
Case disposedDisposed
-
02-May-2026
Order on ExhibitView PDF
-
02-May-2026
Copy of JudgmentView PDF
Case Summary: Jamila Hamid Mahalkar v. Collector & Others (L.A.R. No. 84/2020) Court Decision: The court partly allowed the land acquisition reference, granting applicants enhanced compensation of Rs. 700/- per sq. meter (instead of the originally awarded lower rate) for 3,099.5 sq. meters of land acquired for the Nageshwari Dam project, plus statutory solatium (30%), additional component (12%), and interest. Key Reasoning: The court found the original land acquisition officer's compensation determination flawed—it relied solely on outdated revenue assessments and an unadjusted Ready Reckoner rate, ignoring comparable nearby sales and the land's non-agricultural development potential. Applying proper valuation methodology considering actual market transactions and applying a 65% development cost deduction, the court determined the fair market value at Rs. 700/- per sq. meter, aligned with prior precedent decisions for the same village and project. This case analysis is maintained by casestatus.in based on publicly available court records.
-
02-May-2026
Disposed
Civil Judge Senior Division, Mahad
-
08-Apr-2026
Arguments
Civil Judge Senior Division, Mahad
-
02-Apr-2026
Arguments
Civil Judge Senior Division, Mahad
-
23-Mar-2026
Order on ExhibitView PDF
-
23-Mar-2026
Order on ExhibitView PDF
-
23-Mar-2026
Amended Plaint
Civil Judge Senior Division, Mahad
-
12-Mar-2026
Evidence
Civil Judge Senior Division, Mahad
-
26-Feb-2026
Order on ExhibitView PDF
-
26-Feb-2026
Evidence
Civil Judge Senior Division, Mahad
-
15-Jan-2026
Evidence Part Heard
Civil Judge Senior Division, Mahad
-
01-Jan-2026
Order on ExhibitView PDF
-
01-Jan-2026
Evidence
Civil Judge Senior Division, Mahad
-
11-Dec-2025
Evidence
Civil Judge Senior Division, Mahad
-
06-Nov-2025
Evidence Part Heard
Civil Judge Senior Division, Mahad
-
09-Oct-2025
Evidence Part Heard
Civil Judge Senior Division, Mahad
-
18-Sep-2025
Evidence Part Heard
Civil Judge Senior Division, Mahad
-
14-Aug-2025
Hearing
Civil Judge Senior Division, Mahad
-
24-Jul-2025
Hearing
Civil Judge Senior Division, Mahad
-
10-Jul-2025
List of Witness
Civil Judge Senior Division, Mahad
-
19-Jun-2025
Issues
Civil Judge Senior Division, Mahad
-
10-Apr-2025
Amended Plaint
Civil Judge Senior Division, Mahad
-
20-Mar-2025
Amended Plaint
Civil Judge Senior Division, Mahad
-
06-Mar-2025
Argument on Exh.____Ready
Civil Judge Senior Division, Mahad
-
06-Feb-2025
Argument on Exh.____Ready
Civil Judge Senior Division, Mahad
-
12-Dec-2024
Argument on Exh.____Ready
Civil Judge Senior Division, Mahad
-
05-Dec-2024
Argument on Exh.____Ready
Civil Judge Senior Division, Mahad
-
17-Oct-2024
Argument on Exh.____Ready
Civil Judge Senior Division, Mahad
-
22-Aug-2024
Argument on Exh.____Ready
Civil Judge Senior Division, Mahad
-
13-Jun-2024
Filing of Say on Exh___Ready
Civil Judge Senior Division, Mahad
-
14-Mar-2024
Filing of Say on Exh___Ready
Civil Judge Senior Division, Mahad
-
14-Dec-2023
Filing of Say on Exh___Ready
Civil Judge Senior Division, Mahad
-
12-Oct-2023
First hearing
Initial hearing scheduled
-
17-Sep-2020
Case filed
Registration No. 84/2020
Case Summary: Jamila Hamid Mahalkar v. Collector & Others (L.A.R. No. 84/2020) Court Decision: The court partly allowed the land acquisition reference, granting applicants enhanced compensation of Rs. 700/- per sq. meter (instead of the originally awarded lower rate) for 3,099.5 sq. meters of land acquired for the Nageshwari Dam project, plus statutory solatium (30%), additional component (12%), and interest. Key Reasoning: The court found the original land acquisition officer's compensation determination flawed—it relied solely on outdated revenue assessments and an unadjusted Ready Reckoner rate, ignoring comparable nearby sales and the land's non-agricultural development potential. Applying proper valuation methodology considering actual market transactions and applying a 65% development cost deduction, the court determined the fair market value at Rs. 700/- per sq. meter, aligned with prior precedent decisions for the same village and project. This case analysis is maintained by casestatus.in based on publicly available court records.