Haji Yunus Haji Latif Aghadi And others vs Deputy Collector Land Acquisition And Sub Divisional Office Karjat — 15/2025
Case under Land Acquisition Act Section Section- 28 A (3). Disposed: Contested--PARTLY ALLOWED on 10th April 2026.
L.A.R. - Land Acquisition Reference
CNR: MHRG040024332025
e-Filing Number
05-05-2025
Filing Number
2571/2025
Filing Date
07-05-2025
Registration No
15/2025
Registration Date
07-05-2025
Court
Civil Court Senior Division, Panvel
Judge
4-2nd CIVIL JUDGE S.D.PANVEL
Decision Date
10th April 2026
Nature of Disposal
Contested--PARTLY ALLOWED
Acts & Sections
Petitioner(s)
Haji Yunus Haji Latif Aghadi And others
Basri Haji Yunus Aghadi
Kamran Yunus Aghadi Power Of Attorney holder all Applicant Through
Respondent(s)
Deputy Collector Land Acquisition And Sub Divisional Office Karjat
Hearing History
Judge: 4-2nd CIVIL JUDGE S.D.PANVEL
Disposed
Judgment
Judgment
Judgment
Judgment
| Date | Purpose | Result |
|---|---|---|
| 10-04-2026 | Disposed | |
| 07-04-2026 | Judgment | |
| 06-04-2026 | Judgment | |
| 04-04-2026 | Judgment | |
| 02-04-2026 | Judgment |
Final Orders / Judgements
Court Decision Summary The court partially approved the land acquisition reference case under Section 28-A(3) of the Land Acquisition Act. The court determined that the claimants' agricultural land at Dahivli village, acquired on 18/01/1996 for the Mumbai-Pune highway project, deserves enhanced compensation of Rs. 600 per sq.mt. (instead of Rs. 5,000 per sq.mt. initially offered by the government). The court also awarded 12% annual interest from the notification date until the special officer's award, 30% solatium, and 9-15% interest on the enhanced amount as per statutory provisions, recognizing the land's development potential due to its proximity to major infrastructure and industrial zones. This case analysis is maintained by casestatus.in based on publicly available court records.
Interim Orders
Court Decision Summary The court partially approved the land acquisition reference case under Section 28-A(3) of the Land Acquisition Act. The court determined that the claimants' agricultural land at Dahivli village, acquired on 18/01/1996 for the Mumbai-Pune highway project, deserves enhanced compensation of Rs. 600 per sq.mt. (instead of Rs. 5,000 per sq.mt. initially offered by the government). The court also awarded 12% annual interest from the notification date until the special officer's award, 30% solatium, and 9-15% interest on the enhanced amount as per statutory provisions, recognizing the land's development potential due to its proximity to major infrastructure and industrial zones. This case analysis is maintained by casestatus.in based on publicly available court records.
Browse Related Cases
Cases under same legislation
Explore other courts