Dipak Tulsidas Naik vs Shivdas Mohan Naik — 23/2025
Case under Specific Relief Act Section 34. Status: Reply/Say. Next hearing: 09th June 2026.
R.C.S. - Reg.Civil Suit
CNR: MHNG080002682025
Next Hearing
09th June 2026
e-Filing Number
06-02-2025
Filing Number
39/2025
Filing Date
11-02-2025
Registration No
23/2025
Registration Date
13-02-2025
Court
Civil Court Junior Division , Kamptee
Judge
10-2nd Jt. CJJD and JMFC., Kamptee
Acts & Sections
Petitioner(s)
Dipak Tulsidas Naik
Adv. Sudhanshu Rotkar
Respondent(s)
Shivdas Mohan Naik
Hearing History
Judge: 10-2nd Jt. CJJD and JMFC., Kamptee
Reply/Say
Arguments
Defence Evidence
Defence Evidence
Defence Evidence
| Date | Purpose | Result |
|---|---|---|
| 28-04-2026 | Reply/Say | |
| 24-04-2026 | Arguments | |
| 18-04-2026 | Defence Evidence | |
| 15-04-2026 | Defence Evidence | |
| 08-04-2026 | Defence Evidence |
Interim Orders
Summary: Defendant No. 2's application to set aside the "no written statement" order and file a written statement was rejected. The court found insufficient grounds to permit the late filing, as Defendant No. 2 had failed to file within the 30-90 day period mandated by Order 8 Rule 1 of the CPC, and the case had already progressed to the evidence stage with cross-examinations completed and final arguments pending. Costs awarded in cause. This case analysis is maintained by casestatus.in based on publicly available court records.
Summary: Defendant No. 2's application to set aside the "no written statement" order and file a written statement was rejected. The court found insufficient grounds to permit the late filing, as Defendant No. 2 had failed to file within the 30-90 day period mandated by Order 8 Rule 1 of the CPC, and the case had already progressed to the evidence stage with cross-examinations completed and final arguments pending. Costs awarded in cause. This case analysis is maintained by casestatus.in based on publicly available court records.
Browse Related Cases