Kavita Dilip Sawant and others 4 vs Kamlesh Transport Pvt. Ltd. and another Advocate - KAWARE BAPUSASAHEB RGHUNATH — 24/2021
Case under Workmens Compensation Act, 1923 Section 4. Status: Cross Examination. Next hearing: 02nd April 2026.
Appln WCA C - C
CNR: MHLC200002902021
Filing Number
518/2021
Filing Date
21-Aug-2021
Registration No
24/2021
Registration Date
23-Aug-2021
Court
Labour Court, Aurangabad
Judge
1-Judge, 1st Labour Court, Aurangabad.
Last updated 26-Mar-2026
Acts & Sections
Petitioner(s)
-
1.Kavita Dilip Sawant and others 4
Adv. MUNDADA ANIKET VINOD
-
2.Dnyeshwari Dilip Sawant
Adv. THITE SUNIL SOPAN
-
3.Mahesh Dilip Sawant
Adv. THITE SUNIL SOPAN
-
4.Bhagirathi Bhagvan Savant
Adv. THITE SUNIL SOPAN
-
5.Bhagvan Bhimaji Sawant
Adv. THITE SUNIL SOPAN
Respondent(s)
-
1.Kamlesh Transport Pvt. Ltd. and another Advocate - KAWARE BAPUSASAHEB RGHUNATH
-
2.The Branch Manager, Bajaj Allianz General Insurnace Co. Ltd.
Case History
-
02-Apr-2026
Next hearingPending
-
06-Mar-2026
Cross Examination
Judge, 1st Labour Court, Aurangabad.
-
09-Feb-2026
Cross Examination
Judge, 2nd Labour Court, Aurangabad.
-
07-Feb-2026
Cross Examination
Judge, 2nd Labour Court, Aurangabad.
-
29-Dec-2025
Cross Examination
Judge, 2nd Labour Court, Aurangabad.
-
10-Nov-2025
Cross Examination
Judge, 2nd Labour Court, Aurangabad.
-
09-Oct-2025
Cross Examination
Judge, 2nd Labour Court, Aurangabad.
-
08-Sep-2025
Cross Examination
Judge, 2nd Labour Court, Aurangabad.
-
08-Aug-2025
Cross Examination
Judge, 2nd Labour Court, Aurangabad.
-
10-Jul-2025
Copy of Order Below ExhibitView PDF
Summary: The Labour Court at Aurangabad allowed the respondent's application for framing a preliminary issue regarding the tenability of the claim petition under Section 53 of the ESI Act. The court designated this issue (Issue No. 1(A)) as a preliminary issue and directed parties to lead evidence on it if desired. The respondent was further ordered to file a copy of the proposal/report submitted to ESIC following the accident in question. This case analysis is maintained by casestatus.in based on publicly available court records.
-
10-Jul-2025
Cross Examination
Judge, 2nd Labour Court, Aurangabad.
-
19-Jun-2025
Cross Examination
Judge, 2nd Labour Court, Aurangabad.
-
07-May-2025
Cross Examination
Judge, 2nd Labour Court, Aurangabad.
-
07-Apr-2025
Cross Examination
Judge, 2nd Labour Court, Aurangabad.
-
07-Mar-2025
Cross Examination
Judge, 2nd Labour Court, Aurangabad.
-
07-Feb-2025
Cross Examination
Judge, 2nd Labour Court, Aurangabad.
-
24-Jan-2025
Cross Examination
Judge, 2nd Labour Court, Aurangabad.
-
12-Dec-2024
Cross Examination
Judge, 2nd Labour Court, Aurangabad.
-
27-Nov-2024
Cross Examination
Judge, 2nd Labour Court, Aurangabad.
-
18-Oct-2024
Cross Examination
Judge, 2nd Labour Court, Aurangabad.
-
30-Sep-2024
Cross Examination
Judge, 2nd Labour Court, Aurangabad.
-
28-Aug-2024
Cross Examination
Judge, 2nd Labour Court, Aurangabad.
-
05-Aug-2024
Cross Examination
Judge, 2nd Labour Court, Aurangabad.
-
10-Jul-2024
Cross Examination
Judge, 2nd Labour Court, Aurangabad.
-
28-Jun-2024
Evidence
Judge, 2nd Labour Court, Aurangabad.
-
30-May-2024
Evidence
Judge, 2nd Labour Court, Aurangabad.
-
19-Apr-2024
Evidence
Judge, 2nd Labour Court, Aurangabad.
-
28-Feb-2024
Evidence
Judge, 2nd Labour Court, Aurangabad.
-
24-Jan-2024
Evidence
Judge, 2nd Labour Court, Aurangabad.
-
30-Dec-2023
Evidence
Judge, 2nd Labour Court, Aurangabad.
-
22-Dec-2023
Evidence
Judge, 2nd Labour Court, Aurangabad.
-
21-Nov-2023
Evidence
Judge, 2nd Labour Court, Aurangabad.
-
18-Oct-2023
Evidence
Judge, 2nd Labour Court, Aurangabad.
-
27-Sep-2023
Evidence
Judge, 2nd Labour Court, Aurangabad.
-
07-Sep-2023
Evidence
Judge, 2nd Labour Court, Aurangabad.
-
18-Aug-2023
Evidence
Judge, 2nd Labour Court, Aurangabad.
-
12-Jul-2023
Evidence
Judge, 2nd Labour Court, Aurangabad.
-
07-Jun-2023
Evidence
Judge, 2nd Labour Court, Aurangabad.
-
21-Apr-2023
Evidence
Judge, 2nd Labour Court, Aurangabad.
-
20-Mar-2023
Evidence
Judge, 2nd Labour Court, Aurangabad.
-
17-Feb-2023
Evidence
Judge, 2nd Labour Court, Aurangabad.
-
30-Jan-2023
Say
Judge, 2nd Labour Court, Aurangabad.
-
02-Jan-2023
Say
Judge, 2nd Labour Court, Aurangabad.
-
20-Dec-2022
Say
Judge, 2nd Labour Court, Aurangabad.
-
15-Nov-2022
Say
Judge, 2nd Labour Court, Aurangabad.
-
26-Sep-2022
Say
Judge, 2nd Labour Court, Aurangabad.
-
29-Aug-2022
Say
Judge, 2nd Labour Court, Aurangabad.
-
01-Aug-2022
Say
Judge, 2nd Labour Court, Aurangabad.
-
04-Jul-2022
Say
Judge, 2nd Labour Court, Aurangabad.
-
06-Jun-2022
Issues
Judge, 2nd Labour Court, Aurangabad.
-
20-Apr-2022
Written Statement
Judge, 2nd Labour Court, Aurangabad.
-
30-Mar-2022
Written Statement
Judge, 2nd Labour Court, Aurangabad.
-
05-Mar-2022
Say
Judge, 2nd Labour Court, Aurangabad.
-
10-Feb-2022
Say
Judge, 2nd Labour Court, Aurangabad.
-
17-Jan-2022
Say
Judge, 2nd Labour Court, Aurangabad.
-
21-Dec-2021
Written Statement
Judge, 2nd Labour Court, Aurangabad.
-
20-Nov-2021
Written Statement
Judge, 2nd Labour Court, Aurangabad.
-
12-Oct-2021
Notice
Judge, 2nd Labour Court, Aurangabad.
-
31-Aug-2021
First hearing
Initial hearing scheduled
-
21-Aug-2021
Case filed
Registration No. 24/2021
Summary: The Labour Court at Aurangabad allowed the respondent's application for framing a preliminary issue regarding the tenability of the claim petition under Section 53 of the ESI Act. The court designated this issue (Issue No. 1(A)) as a preliminary issue and directed parties to lead evidence on it if desired. The respondent was further ordered to file a copy of the proposal/report submitted to ESIC following the accident in question. This case analysis is maintained by casestatus.in based on publicly available court records.