Gunderao S/o Maroti Tarde and other 1 vs Prashant S/o Prabhakar Bhalke and other 4 Advocate - Patil Suhas G — 556/2025

Case under Code of Civil Procedure Section 26. Status: Order on Exh. Next hearing: 17th June 2026.

R.C.S. - Regular Civil Suit

CNR: MHLA060026872025

Order on Exh

Next Hearing

17th June 2026

e-Filing Number

19-08-2025

Filing Number

1120/2025

Filing Date

19-08-2025

Registration No

556/2025

Registration Date

19-08-2025

Court

Civil Court Junior Division , Ahmedpur

Judge

1-Jt.Civil Judge J.D. And J.M.F.C. Ahmedpur

Acts & Sections

CODE OF CIVIL PROCEDURE Section 26

Petitioner(s)

Gunderao S/o Maroti Tarde and other 1

Adv. Phad Sangram B

Hulappa S/o Nivrutti Tarde

Adv. Phad Sangram B

Respondent(s)

Prashant S/o Prabhakar Bhalke and other 4 Advocate - Patil Suhas G

Nishant S/o Prabhakar Bhalke

Adv. Patil Suhas G

Kamalbai Prabhakar Bhalke

Adv. Patil Suhas G

Sai Datta Green Anergy Pra Ltd Office Through Nagnath Ramrao Patil

Adv. Kshirsagar Bharatbhushen B

Sai Datta Green Pra Ltd Through Meera Vasantrao Shirure

Adv. Kshirsagar Bharatbhushen B

Hearing History

Judge: 1-Jt.Civil Judge J.D. And J.M.F.C. Ahmedpur

06-05-2026

Order on Exh

17-04-2026

Order on Exh

04-04-2026

Order on Exh

13-03-2026

Order on Exh

16-02-2026

Order on Exh

Interim Orders

29-10-2025
Order on Exhibit

Case Summary: RCS No. 556/2025 The court partially allowed the plaintiffs' application for status quo/temporary injunction on 29 October 2025. The plaintiffs sought to restrain defendants from damaging their pipeline passing through land in village Thodga (gat No.21). The court granted status quo only regarding the land in the name of defendant No.1, ordering all parties to maintain the pipeline's current position until further order, as defendant No.1 was a party to the consent deed granting easementary rights. The court rejected relief regarding defendant No.2's land as she was not party to the consent deed. Plaintiffs must comply with CPC Order 39 Rule 3(a) and report compliance to the court. This case analysis is maintained by casestatus.in based on publicly available court records.

casestatus.in Summary

Case Summary: RCS No. 556/2025 The court partially allowed the plaintiffs' application for status quo/temporary injunction on 29 October 2025. The plaintiffs sought to restrain defendants from damaging their pipeline passing through land in village Thodga (gat No.21). The court granted status quo only regarding the land in the name of defendant No.1, ordering all parties to maintain the pipeline's current position until further order, as defendant No.1 was a party to the consent deed granting easementary rights. The court rejected relief regarding defendant No.2's land as she was not party to the consent deed. Plaintiffs must comply with CPC Order 39 Rule 3(a) and report compliance to the court. This case analysis is maintained by casestatus.in based on publicly available court records.