Ramani vs Uthaman — 300636/2014
Case under Code of Civil Procedure Section 26. Status: Verify and report. Next hearing: 17th June 2026.
OS - ORIGINAL SUIT
CNR: KLTV430007062014
Next Hearing
17th June 2026
Filing Number
5876/2014
Filing Date
21-11-2014
Registration No
300636/2014
Registration Date
21-11-2014
Court
Munsiff Court Attingal
Judge
1-MUNSIFF ATTINGAL
Acts & Sections
Petitioner(s)
Ramani
Adv. Chirayinkeezhu G. Surendran
Respondent(s)
Uthaman
Hearing History
Judge: 1-MUNSIFF ATTINGAL
Verify and report
For commission report
For commission report
For commission report
For hearing on IA
| Date | Purpose |
|---|---|
| 22-05-2026 | Verify and report |
| 12-03-2026 | For commission report |
| 30-01-2026 | For commission report |
| 01-12-2025 | For commission report |
| 04-11-2025 | For hearing on IA |
Interim Orders
Court Order Summary Petition Allowed. The Munsiff Court of Attingal granted the plaintiff's petition to amend the plaint to include allegations that the defendant destroyed the southern boundary on 24.11.2014 and seek relief for constructing a compound wall. The court found the amendment necessary to determine the real dispute between parties and rejected the defendant's time-bar defense, holding that amendments need not be rejected merely because relief is time-barred if no new cause of action is introduced. The plaintiff must complete the amendment within 14 days and pay costs of Rs. 1,500 to the defendant. This case analysis is maintained by casestatus.in based on publicly available court records.
Court Order Summary Petition Allowed. The Munsiff Court of Attingal granted the plaintiff's petition to amend the plaint to include allegations that the defendant destroyed the southern boundary on 24.11.2014 and seek relief for constructing a compound wall. The court found the amendment necessary to determine the real dispute between parties and rejected the defendant's time-bar defense, holding that amendments need not be rejected merely because relief is time-barred if no new cause of action is introduced. The plaintiff must complete the amendment within 14 days and pay costs of Rs. 1,500 to the defendant. This case analysis is maintained by casestatus.in based on publicly available court records.