Swoparnika Projects and Infrastructure Pvt. Ltd. rep. by JoJi Joseph vs Shajahan N Advocate - Rajeev Chempakassery, VIPIN KUMAR V P — 200057/2021
Case under Code of Civil Procedure Section 26. Disposed: Uncontested--SETTLED OUT COURT. on 18th March 2026.
OS - ORIGINAL SUIT
CNR: KLTV330003842021
Filing Number
228/2021
Filing Date
10-11-2021
Registration No
200057/2021
Registration Date
10-11-2021
Court
Sub Court Nedumangadu
Judge
1-SUB JUDGE AND ASSISTANT SESSIONS JUDGE NEDUMANGAD
Decision Date
18th March 2026
Nature of Disposal
Uncontested--SETTLED OUT COURT.
Acts & Sections
Petitioner(s)
Swoparnika Projects and Infrastructure Pvt. Ltd. rep. by JoJi Joseph
Adv. AMAR DILEEP
Respondent(s)
Shajahan N Advocate - Rajeev Chempakassery, VIPIN KUMAR V P
Noorjahan Shajahan
Adv. G.S Rajeev Chempakassery,VIPIN KUMAR V P
Hearing History
Judge: 1-SUB JUDGE AND ASSISTANT SESSIONS JUDGE NEDUMANGAD
Disposed
FOR HEARING
Await mediation report
call on
Issues
| Date | Purpose |
|---|---|
| 18-03-2026 | Disposed |
| 13-03-2026 | FOR HEARING |
| 05-03-2026 | Await mediation report |
| 28-02-2026 | call on |
| 03-01-2026 | Issues |
Final Orders / Judgements
The court decreed the suit in favor of Souparnika Projects and Infrastructure Pvt. Ltd. based on a mediated settlement, ordering defendants Shajahan N and Noorjahan Shajahan to pay Rs. 65 lakhs in two installments (Rs. 40 lakhs by March 7, 2026 and Rs. 25 lakhs by March 31, 2026). The court found the settlement lawful and accepted the mediation agreement, with a default clause allowing recovery of Rs. 77,74,794 plus 9% interest from property if payment defaults occur. This case analysis is maintained by casestatus.in based on publicly available court records.
The court decreed the suit in favor of Souparnika Projects and Infrastructure Pvt. Ltd. based on a mediated settlement, ordering defendants Shajahan N and Noorjahan Shajahan to pay Rs. 65 lakhs in two installments (Rs. 40 lakhs by March 7, 2026 and Rs. 25 lakhs by March 31, 2026). The court found the settlement lawful and accepted the mediation agreement, with a default clause allowing recovery of Rs. 77,74,794 plus 9% interest from property if payment defaults occur. This case analysis is maintained by casestatus.in based on publicly available court records.