Kalyanadayini Sabha vs Mohammed Shafi — 101098/2023

Case under Code of Civil Procedure Section Order7Rule1. Disposed: Uncontested--DECREED WITH COST on 11th March 2026.

OS - ORIGINAL SUIT

CNR: KLTR190027112023

Case disposed

e-Filing Number

22-10-2023

Filing Number

102689/2023

Filing Date

25-10-2023

Registration No

101098/2023

Registration Date

25-10-2023

Court

Munsiffcourt, Kodungallur

Judge

1-MUNSIFF KODUNGALLUR

Decision Date

11th March 2026

Nature of Disposal

Uncontested--DECREED WITH COST

Acts & Sections

CODE OF CIVIL PROCEDURE Section Order7Rule1

Petitioner(s)

Kalyanadayini Sabha

Adv. Prathapan K N

Muhamed Shafi

Adv. PRATHAPAN K N

Pradeepkumar

Adv. PRATHAPAN K N

Sunilkumar

Adv. PRATHAPAN K N

Unnikrishnan

Adv. PRATHAPAN K N

Respondent(s)

Mohammed Shafi

Pradeep Kumar

sunilkumar

Unnikrishnan

Hearing History

Judge: 1-MUNSIFF KODUNGALLUR

11-03-2026

Disposed

03-03-2026

Order/ Judgement

01-12-2025

Adjourned

21-11-2025

Adjourned

12-11-2025

Adjourned

Final Orders / Judgements

11-03-2026
Judgement

The Munsiff Court of Kodungallur decreed the suit filed by Kalyanadayini Sabha against four defendants for recovery of Rs. 2,40,800/- on a defaulted kuri (rotating credit scheme) loan agreement dated 15.11.2011. The court held the defendants liable since they remained absent (ex parte), leaving the plaintiff's unchallenged evidence of the loan agreement and default notice intact. The defendants are ordered to pay the principal amount with 12% interest from suit date to decree date, and 6% thereafter, plus entire suit costs. This case analysis is maintained by casestatus.in based on publicly available court records.

casestatus.in Summary

The Munsiff Court of Kodungallur decreed the suit filed by Kalyanadayini Sabha against four defendants for recovery of Rs. 2,40,800/- on a defaulted kuri (rotating credit scheme) loan agreement dated 15.11.2011. The court held the defendants liable since they remained absent (ex parte), leaving the plaintiff's unchallenged evidence of the loan agreement and default notice intact. The defendants are ordered to pay the principal amount with 12% interest from suit date to decree date, and 6% thereafter, plus entire suit costs. This case analysis is maintained by casestatus.in based on publicly available court records.