stephen jobe vs ATC (American Tower Corporation) — 300288/2024
Case under Code of Civil Procedure Section 26order7rule1. Status: Pre trial steps. Next hearing: 16th July 2026.
OS - ORIGINAL SUIT
CNR: KLPT130004472024
e-Filing Number
27-09-2024
Filing Number
514/2024
Filing Date
27-Sep-2024
Registration No
300288/2024
Registration Date
27-Sep-2024
Court
Munsiff Court, Thiruvalla
Judge
1-Munsiff
Last updated 13-May-2026
Acts & Sections
Petitioner(s)
-
1.stephen jobe
Adv. JACOB THOMAS
-
2.Jacob Thampy
Adv. JACOB THOMAS
Respondent(s)
-
1.ATC (American Tower Corporation)
-
2.Ramesh Elamon Namboothiri
Case History
-
16-Jul-2026
Next hearingPending
-
11-Mar-2026
Pre trial steps
Munsiff
-
02-Dec-2025
Pre trial steps
Munsiff
-
07-Oct-2025
Issues
Munsiff
-
13-Aug-2025
Issues
Munsiff
-
27-Jun-2025
Issues
Munsiff
-
01-Apr-2025
Written Statement
Munsiff
-
11-Dec-2024
OrderView PDF
-
11-Dec-2024
OrderView PDF
Summary The petition filed by Stephen Jobe and Jacob Thampi seeking temporary injunction to prevent construction of a 5G telecom tower on neighboring property was dismissed. The court found no prima facie case and ruled that the tower construction complies with Kerala Municipal Building Rules (minimum 1.20 meters distance requirement met) and the District Telecom Committee's order dated 12.09.2024 permits the work. The Specific Relief Act bars injunctions that would delay infrastructure projects like telecommunications towers. This case analysis is maintained by casestatus.in based on publicly available court records.
-
11-Dec-2024
Written Statement
Munsiff
-
10-Dec-2024
Order/Judgement
Munsiff
-
05-Dec-2024
Order/Judgement
Munsiff
-
26-Nov-2024
Order/Judgement
Munsiff
-
20-Nov-2024
For further hearing
Munsiff
-
16-Nov-2024
For hearing on IA
Munsiff
-
11-Nov-2024
Return of summons
Munsiff
-
27-Sep-2024
First hearing
Initial hearing scheduled
-
27-Sep-2024
Case filed
Registration No. 300288/2024
Summary The petition filed by Stephen Jobe and Jacob Thampi seeking temporary injunction to prevent construction of a 5G telecom tower on neighboring property was dismissed. The court found no prima facie case and ruled that the tower construction complies with Kerala Municipal Building Rules (minimum 1.20 meters distance requirement met) and the District Telecom Committee's order dated 12.09.2024 permits the work. The Specific Relief Act bars injunctions that would delay infrastructure projects like telecommunications towers. This case analysis is maintained by casestatus.in based on publicly available court records.
Explore other courts