Sebastian V J vs Power Grid Corporation of India Ltd. Advocate - SUNNY GEORGE — 252/2019
Case under Indian Telegraph Act Section 10,16. Disposed: Contested--ALLOWED on 23rd May 2026.
OP - ORIGINAL PETITION
CNR: KLKT010035432019
Filing Number
1470/2019
Filing Date
20-11-2019
Registration No
252/2019
Registration Date
22-11-2019
Court
Principal District & Sessions Court / Rent Control Appellate Authority, Kottayam
Judge
2-Addl. District and Sessions Judge - I, Kottayam
Decision Date
23rd May 2026
Nature of Disposal
Contested--ALLOWED
Acts & Sections
Petitioner(s)
Sebastian V J
Adv. THOMAS JOSEPH
Varkey V O
Kurian V O
Mary Ouseph
Ulahannan Ouseph
Respondent(s)
Power Grid Corporation of India Ltd. Advocate - SUNNY GEORGE
Special Tahasildar
Adv. Meera S.S. (Addl. Govt Pleader and Public Prosecutor, Kottayam)
District Collector
Adv. Meera S.S. (Addl. Govt Pleader and Public Prosecutor, Kottayam)
KSEB,Thiruvanathapuram
Adv. Deepthi S Nath
Hearing History
Judge: 2-Addl. District and Sessions Judge - I, Kottayam
Disposed
Order/Judgement
Order/Judgement
Order/Judgement
Order/Judgement
| Date | Purpose |
|---|---|
| 23-05-2026 | Disposed |
| 22-05-2026 | Order/Judgement |
| 20-05-2026 | Order/Judgement |
| 18-05-2026 | Order/Judgement |
| 16-05-2026 | Order/Judgement |
Final Orders / Judgements
Case Summary: OP 252/2019 Court Decision: The petition was allowed in favor of the petitioners. The Additional District Judge-I, Kottayam ordered Power Grid Corporation of India Ltd. to pay enhanced compensation for property damage caused by a 400 KV electrical transmission line. Key Rulings: The court awarded ₹17,88,404 for land value diminution (50% of market value for the affected 20.89 cents) and ₹3,59,279 for trees cut, with 7% annual interest from September 7, 2018 until payment, rejecting the petitioners' claim for 12% interest and their ₹5 crore diminution claim as excessive. This case analysis is maintained by casestatus.in based on publicly available court records.
Case Summary: OP 252/2019 Court Decision: The petition was allowed in favor of the petitioners. The Additional District Judge-I, Kottayam ordered Power Grid Corporation of India Ltd. to pay enhanced compensation for property damage caused by a 400 KV electrical transmission line. Key Rulings: The court awarded ₹17,88,404 for land value diminution (50% of market value for the affected 20.89 cents) and ₹3,59,279 for trees cut, with 7% annual interest from September 7, 2018 until payment, rejecting the petitioners' claim for 12% interest and their ₹5 crore diminution claim as excessive. This case analysis is maintained by casestatus.in based on publicly available court records.
Browse Related Cases
Cases under same legislation
Explore other courts