M M Sasi vs Power Grid Corporation of India Ltd. — 18/2023
Case under Indian Telegraph Act Section 10,16. Disposed: Contested--ALLOWED on 16th March 2026.
OP - ORIGINAL PETITION
CNR: KLKT010009762023
Filing Number
100403/2023
Filing Date
06-02-2023
Registration No
18/2023
Registration Date
06-02-2023
Court
Principal District & Sessions Court / Rent Control Appellate Authority, Kottayam
Judge
3-Addl. District and Sessions Judge - II (Spl.) / Addl. MACT-I, Kottayam
Decision Date
16th March 2026
Nature of Disposal
Contested--ALLOWED
Acts & Sections
Petitioner(s)
M M Sasi
Adv. GANGA PRASAD S
V K Omana
Respondent(s)
Power Grid Corporation of India Ltd.
Hearing History
Judge: 3-Addl. District and Sessions Judge - II (Spl.) / Addl. MACT-I, Kottayam
Disposed
Order/Judgement
Order/Judgement
Order/Judgement
Order/Judgement
| Date | Purpose |
|---|---|
| 16-03-2026 | Disposed |
| 11-03-2026 | Order/Judgement |
| 10-03-2026 | Order/Judgement |
| 27-02-2026 | Order/Judgement |
| 24-02-2026 | Order/Judgement |
Final Orders / Judgements
The court awarded enhanced compensation of ₹28,89,908.55 to the petitioners for inadequate tree and land value compensation paid by Power Grid Corporation during construction of a 400 KV electricity transmission line across their property. The court applied a 10-year multiplier for yielding trees and calculated compensation based on expected future yields for non-yielding trees; it also awarded 40-50% diminution in land value depending on the line's location on affected parcels, plus 8% interest from April 2019. This case analysis is maintained by casestatus.in based on publicly available court records.
The court awarded enhanced compensation of ₹28,89,908.55 to the petitioners for inadequate tree and land value compensation paid by Power Grid Corporation during construction of a 400 KV electricity transmission line across their property. The court applied a 10-year multiplier for yielding trees and calculated compensation based on expected future yields for non-yielding trees; it also awarded 40-50% diminution in land value depending on the line's location on affected parcels, plus 8% interest from April 2019. This case analysis is maintained by casestatus.in based on publicly available court records.