Jagalur Hanumanthappa alias Hanumanthappa S/o Nagappa alias Late Nagappa vs The Executive Engineer-KPTCL Ballari. — 5201/2024
Case under Indian Telegraph Act Section 16(3). Disposed: Contested--DISMISSED on 07th March 2026.
Misc - Miscellaneous Cases
CNR: KAVN010014992024
e-Filing Number
-
Filing Number
5201/2024
Filing Date
01-10-2024
Registration No
5201/2024
Registration Date
01-10-2024
Court
PRL. DISTRICT AND SESSIONS COURT, VIJAYANAGARA
Judge
983-ADDL DISTRICT AND SESSIONS JUDGE VIJAYANAGARA DISTRICT HOSAPETE
Decision Date
07th March 2026
Nature of Disposal
Contested--DISMISSED
Acts & Sections
Petitioner(s)
Jagalur Hanumanthappa alias Hanumanthappa S/o Nagappa alias Late Nagappa
Adv. K.C. Nagaraj
Respondent(s)
The Executive Engineer-KPTCL Ballari.
Hearing History
Judge: 983-ADDL DISTRICT AND SESSIONS JUDGE VIJAYANAGARA DISTRICT HOSAPETE
Disposed
JUDGMENT/FINAL ORDER
EVIDENCE-C
WRITTEN STATEMENTS/OBJECTION TO MAIN PETITION-C
WRITTEN STATEMENTS/OBJECTION TO MAIN PETITION-C
| Date | Purpose | Result |
|---|---|---|
| 07-03-2026 | Disposed | |
| 23-02-2026 | JUDGMENT/FINAL ORDER | |
| 19-01-2026 | EVIDENCE-C | |
| 15-11-2025 | WRITTEN STATEMENTS/OBJECTION TO MAIN PETITION-C | |
| 16-08-2025 | WRITTEN STATEMENTS/OBJECTION TO MAIN PETITION-C |
Final Orders / Judgements
Summary The court dismissed the petitioner's petition for compensation for alleged damages from a 66 KV power transmission line drawn across his land by Karnataka Power Transmission Company Limited (KPTCL). The petition was time-barred under Article 137 of the Limitation Act 1963, as the power line was drawn on 01.01.1993 but the petition was filed in 2024—over 31 years later, exceeding the three-year limit. Additionally, the petitioner failed to produce supporting documentary evidence for his claimed Rs. 40,00,000 compensation. This case analysis is maintained by casestatus.in based on publicly available court records.
Interim Orders
Summary The court dismissed the petitioner's petition for compensation for alleged damages from a 66 KV power transmission line drawn across his land by Karnataka Power Transmission Company Limited (KPTCL). The petition was time-barred under Article 137 of the Limitation Act 1963, as the power line was drawn on 01.01.1993 but the petition was filed in 2024—over 31 years later, exceeding the three-year limit. Additionally, the petitioner failed to produce supporting documentary evidence for his claimed Rs. 40,00,000 compensation. This case analysis is maintained by casestatus.in based on publicly available court records.